| Tennessee Report Hot
spots keep state's economy rolling By Candy McCampbell Even
though economic forecasts say construction job growth in Tennessee is expected
to slow to 1.1 percent this year, there continues to be high levels of building,
particularly in Nashville and its suburbs, Franklin, Murfreesboro, Hendersonville
and Gallatin. "It's booming," says Pete Dickson, president of
Associated Builders and Contractors of Middle Tennessee in Nashville. "Designers
report plenty of work coming in. In fact, they're overwhelmed." Among
the projects under construction are the $80 million Icon condominiums, the $100
million Nissan headquarters in Franklin, a $30 million interchange on Interstate
65 nearby, the $50 million Avenue Shopping Center in Murfreesboro and the $39
million airport terminal renovation. Also this year, look for the start
of the Nashville Sounds' new $43 million baseball stadium. "This (Nashville
area) has been a profitable sector longer than anyone thought it would be,"
says Connie Wallace, executive vice president of the Tennessee Chapter, American
Institute of Architects.
Roger Tuder, executive director of Associated General Contractors of East Tennessee,
says the Chattanooga area is also experiencing a robust construction environment,
and he credits "a strong economy" for an abundance of public- and private-sector
projects. The biggest Chattanooga-area project by far is Blue Cross Blue
Shield's 900,000-sq-ft headquarters and 4,100-vehicle parking garage. Also under
way are expansions at two hospitals, 890,000 sq. ft. of new schools and eight
new churches. In Knoxville, work continues on Interstate 40 as part of the
state's costliest-ever highway project. Also, the city's downtown is getting a
facelift with a $27 million CityView at Riverwalk condo/marina development and
construction of the new Interstate 475 may soon be started. It's not as
bright in the Memphis area. "We're looking at a slowdown in 2007 and
to pick back up in 2008," says Bob Rose, executive director of Associated
General Contractors of West Tennessee. The outlook for Memphis could change
if Toyota selects a west Tennessee or eastern Arkansas site for a new assembly
plant. Following are a few of the significant projects under construction: Signature
Tower, Nashville. By mid-2009, the Southeast's tallest building will be
a 65-story structure in downtown Nashville with 400 condo units atop a 10-story
Kimpton Hotel. Turner Construction of New York has the $275 million contract
and broke ground early this year on the 1,052-ft-tall reinforced-concrete tower.
It's a tight spot for construction, especially since the job involves excavating
about 90 ft. deep into rock for the seven-story parking garage and foundation,
says Ed Baldwin, purchasing manager. The site also has churches on three
sides and borders a major throughfare on the fourth. Getting all the rock
out will require both power equipment and blasting, Baldwin says. "There
a lot of constraints involved - noise, damage to adjacent structures and to underground
utilities - but I think they can be mitigated," he adds. Morgan
County Correctional Complex, Wartburg. Bell & Associates Construction
of Brentwood, Tenn., currently holds a $151 million contract to build a 500,000-sq-ft,
20-building prison in Wartburg, Tenn. Included in the job are 1,430 maximum-,
medium- and minimum-security beds and administration, visitation, medical, food
service and support buildings. Two other buildings onsite will be renovated, totaling
almost 50,000 sq ft. Completion of the maintenance building in January
allowed demolition of the existing maintenance building and start of the food
service-dining-laundry building. "We accomplished a major milestone
- to get all the concrete slabs poured before winter set in," says Kevin
Keller, project manager with Bell. The cells are prefabricated units that
are trucked in and lifted in place. Crews on site complete water and electrical
connections once the units are in place. Gateway
Regional Medical Center, Clarksville. BE&K Building Group of Brentwood,
Tenn., topped out the steel on this $120 million, 503,000-sq-ft complex in early
January, six months after starting. "We have had good weather and have
some great subs," said Jason Adams, project manager for BE&K. Work
on the five-story building started in July and completion is expected in summer
2008. Adams says that while some crews were still working on the first-floor
steel, others were framing interior and exterior walls on three floors of the
tower. The footprint for the first floor is 270,000 sq ft, while the upper
floors are about 55,000 sq ft. The first floors will house an emergency room with
37 exam rooms and 12 operating rooms. The building sits on stone columns
with spread footings and high-pressure cap grouting foundations. Adams says
materials needed include 3,100 tons of structural steel, 145 tons of rebar and
11,340 cu yds of concrete. I-40 near I-275 to
Cherry Street, Knoxville. Bell & Associates Construction LP of Brentwood,
Tenn., formerly Ray Bell Construction, is widening I-40 from two lanes to three
in this $104.7 million job, a joint venture with Blalock and Sons of Sevierville,
Tenn. The interstate reconstruction contract is the state's largest road
job, topping Bell's $85 million contract for an adjacent jobsite. The entire
project, to finish in 2009, is being built under a Tennessee Department of Transportation
process that allows road closures to speed work. It's expected to cut almost two
years from the timeline. Started in June, the contract also includes widening
two bridges and replacing 11 more, says Jeremy Mitchell, project manager for Bell
& Associates. The road changes also necessitate about $3.6 million in
utility relocation. A total of 100,000 sq ft of noise wall and 70,000 sq
ft of retaining wall are going up. Workers are moving more than 500,000 cu yds
of dirt for road work and drainage and bringing in another 100,000 cu yds, Mitchell
says. Cofferdam Construction, Chickamauga Lock,
Chattanooga. Work is expected to start this month on a 1,060- by 3,100-ft
cofferdam at Chickamauga Dam on the Tennessee River near Chattanooga. The cofferdam
is needed to construct a new 100- by 600-ft lock structure, which will replace
an existing 1940s-era lock. C. J. Mahan Construction of Grove City, Ohio,
has the $82.9 million contract with the U.S. Army Corps of Engineers, which operates
the lock for the Tennessee Valley Authority. Mahan will set circular templates
made of H-piles, then drive pieces of sheet pile, which are then welded to the
templates, says Jason Pieton, Mahan's project manager. Crews will operate
from "at least a half dozen barges," he said. The cofferdam will displace
about 1 million gallons of water. The river's barge traffic will dictate
some schedules, Pieton says. "We can't hinder barge traffic at all,"
he says. "We have to work around it." Encore
Condominium Tower, Nashville. Building a 20-story high-rise in downtown
Nashville means working with certain limitations. "We have lane closures
when we pour concrete," says Bob Watson, senior project manager for Brasfield
& Gorrie Inc. of Birmingham. So pours for the $55 million, 580,000-sq-ft
tower are usually about 2 a.m.-4 a.m. or 6 p.m. Crews also got a street closure
while installing an electrical duct bank. The building covers 40,000 sq
ft, roughly half the block it sits on. The ground floor will include 20,000 sq
ft of retail. The next six levels are a parking garage and affordable housing
units on one side. The building narrows to a 20,000 sq. ft. floor plate above
the seventh floor, location of the pool and amenity deck, Watson says. The
building is post-tensioned concrete, on a drill-pier foundation. The 333 units
will have floor-to-ceiling glass and many ceilings will be exposed concrete. FedEx
Airbus Hangar Facility, Memphis. The first hangar in this hemisphere for
the Airbus A-380 became a maintenance hangar for the Boeing 777 after FedEx changed
aircraft manufacturers last fall. Hunt Construction Group of Dallas is building
the $75 million, 281,000-sq-ft project. It includes a 140,000-sq-ft maintenance
hangar, a 73,000-sq-ft office building, a 48,000-sq-ft warehouse and a 20,000-sq.-ft.
shop, says Benton Hagler, senior estimator. The hangar will have a 400-ft
clear span with roof trusses that are 45 ft deep. The 145-ft-tall structure will
measure 400 by 310 ft. "The biggest difference in this and other hangars
is the span and the height," Hagler says. The foundation is drill-pier
footings and concrete piers around the building edge. The reinforced slab will
be 16 in. thick. Exterior walls are metal. The hangar can house one of the big
planes or two conventional jets. Construction started early this year, with an
April 2008 completion. Hill Center at Green Hills,
Nashville. The Hill Center at Green Hills, a $70 million mixed-use lifestyle
project, is replacing an old 1960s strip shopping center that is in the middle
of a busy suburban shopping/restaurant area. Hoar Construction of Birmingham
is the construction manager for the 222,000-sq-ft project that includes 162,000
sq ft of retail and restaurant space and 60,000 sq ft of office space. Workers
had to demolish the old center and some outlying buildings before construction
could start. That included excavation of more than 60,000 cu yds of rock to build
the parking garage. The buildings are being constructed on both sides of
a central street that cuts through the 10-acre site. Construction started
in September 2005 and should be completed later this year. Healthways
Inc. Headquarters, Franklin. Healthways Inc., formerly American Healthways,
will move about 600 employees to its 275,000-sq-ft headquarters and is providing
a 585-car parking garage for their vehicles. Brasfield & Gorrie of Birmingham
has the $36 million contract for the building shell - with 61,000 sq ft of basement
parking - and detached garage. Interior tenant build-out is under a separate contract. The
five-story building has a spread footings foundation and workers hit rock at an
average 3-5 ft., says David Gordon, Brasfield & Gorrie project manager. "The
exterior skin will be a combination of architectural precast, punched opening
windows and curtain wall systems," he adds Start date was July, and
shell completion is scheduled for January 2008. |