|
Concrete update
Despite rising cost, material still
popular option on South Central jobs
By Candy McCampbell
Cost-effective and environmentally friendly concrete continues
to be a popular building material throughout the South Central
region.
In use since before the Romans built aqueducts in France,
concrete is currently going into South Central projects as
diverse as a Little Rock hospital, a Gulfside condo tower,
a Beale Street hotel and a Birmingham church activity center.
"You can color, stamp, stain, mold and form unique structures
out of concrete that have many other attributes," said
Heather Brown, interim director of the Concrete Industry Management
Program at Middle Tennessee State University in Murfreesboro.
"It is sound, wind and earthquake resistant," Brown
said. And its energy efficiency is "key to consumers."
Concrete is "earth-friendly," said Robert Varner,
executive director of the Mississippi Concrete Industries
Association.
Its cement, sand and water base are "abundant natural
resources" and, after use, concrete can be broken up
and re-used for things such as base material for roads, he
said.
It's also low-maintenance, said John Eggers, senior concrete
research engineer at the Louisiana Transportation Research
Center in Baton Rouge.
"Properly constructed concrete structures also do not
require the maintenance or protection from the elements that
steel would require," he added.
Concrete's higher use also comes from the additives to the
"mix."
"We can now pour concrete in extreme weather, underwater,
30 floors up or in tight spaces where equipment or manpower
can not go," Brown said.
In addition, when cement is scarce "a myriad of cementitious
byproducts can allow the structure to be at the same performance
[level] but cost a little less and help the environment."
The main reason for concrete's popularity is that "it
is the most economical material for most large structures,"
Eggers said.
Sure, prices are higher, but that is happening across the
supply board, Brown said.
"If all costs were equal, concrete would still be at
the top of the list because of the durability and life you
can achieve out of concrete," she said.
As prices of cement rise, look for greater use of fly ash
and slag to replace it while adding strength to concrete,
Eggers said.
"Both slag and fly ash are cheaper pound for pound than
cement," he said.
They have become increasingly popular in recent decades as
a cost-cutter and as owners seek stronger and more durable
material.
Meanwhile, concrete supplies have been tight because of domestic
plant shutdowns for maintenance and demand from China, which
is gearing up for the 2008 Olympic games.
"All the rebuilding and growth will have some impact
on demand," Varner said.
Concrete consumption has been up this year, but the Portland
Cement Association recently revised its forecast downward,
projecting 2.3 percent growth over last year due to higher
interest rates, higher oil prices and inflation. It earlier
predicted a 3.5 percent increase in consumption.
Following are some of the larger projects currently under
way in the South Central region.
Turquoise Place, Towers I and II,
Orange Beach, Ala. The $110 million Turquoise Place,
Tower I, in Orange Beach, Ala., will soon top out and work
is starting on Tower II.
Housing 400 luxury condominiums, Tower I will be 304 ft.
tall and Tower II will rise to 377 ft., said George Yates,
project manager with general contractor Yates Construction
of Biloxi, Miss.
With floor slabs in the 33,000-sq.-ft. to 35,000-sq.-ft.
range, the buildings will require about 110,000 cu. yds. of
concrete.
The buildings have post-tensioned decks and concrete and
rebar columns and sheer walls.
The towers sit on 20-in. auger-cast compression and tension
piles that were drilled about 65 ft. to a sand layer, he said.
Each tower is fronted with a four-story parking garage. Exterior
walls will be a glass curtain wall extension of turquoise
glass.
Applied Sciences Building, The
University of Alabama, Huntsville, Ala. More than 1,000
rammed aggregate piers, driven down about 30 ft. to rock,
support this $60 million four-story, 207,000-sq.-ft. building.
The procedure was quicker than building concrete caissons,
and saved both money and about one month of construction time,
said Marty Miller, project manager with construction manager
Turner Universal of Huntsville, Ala.
An early surprise was a "subterranean void" that
- thanks to designs by the geotechnical and structural engineers
- got an injection of pressurized grouting, he said.
The cast-in-place concrete building has pan joist floors
with 4.5-in. slabs.
The building will house laboratories, so 100 lab fume hoods
and a dedicated laboratory exhaust system were installed.
Supply and exhaust systems also have redundant fans, he said.
The lab exhaust system has a heat recovery system to pre-cool
outside air and lower air-conditioning energy consumption.
The exterior walls are limestone, precast concrete and granite
with curtain wall windows. The roof is SBS modified bitumen
membrane.
Monolithic dome activity center,
Faith Chapel Christian Center, Birmingham, Ala. Build
six round forms, cover each with roofing membrane, inflate
that and start spraying inside with layers of shotcrete and
insulating foam.
Constructing the six domes in this $16.5 million church expansion
project is almost that simple, said William Robertson, construction
manager with Monumental Contracting Service of Birmingham,
Ala. It's a little more detailed - the domes must be lined
with rebar and interiors must be finished out.
The domes range in size from 27,228 sq. ft. to 14,952 sq.
ft., and will require 3,450 cu. yds. of concrete and 330 tons
of steel.
One dome goes up about every two months, he said. When all
six are finished, subs will start on the interiors, moving
directly from one to the next.
The base walls - from 10 ft. to 14 ft. tall - are built in
much the same way as the dome. The wall form is lined with
the woven rebar and sprayed with shotcrete and insulating
polyurethane foam.
Parking deck, Arkansas Children's
Hospital, Little Rock. When the building site is surrounded
by city streets and other buildings, it makes sense to pre-build
elements offsite and assemble them after delivery.
That's what is happening at this $12 million, four-level
parking deck, said Larry Beckius, vice president for facilities
at the hospital. "It's put together like Lincoln Logs."
The project's general contractor is Nabholz Construction
of Conway, Ark.
The columns and beams are all precast and trucked in from
Oklahoma and Texas, and columns are bolted in place.
The floors are post-tensioned concrete.
The parking deck, next to a hospital-related office building,
is four separate and unconnected levels, each entered from
one of the surrounding streets in the hilly city. Its 1,000
spaces will be assigned for hospital employees.
The foundation is 151 drill piers, sunk about 25 ft., he
said.
The floors were being poured in August, at a rate of about
24,000 cu. yds. a week. The structure will use about 111,000
cu. yds. of concrete and 600 tons of reinforcing steel. Walls
more than 8 ft. tall are 12 in. thick, while shorter ones
are 8 in.
Hospital addition, University of
Arkansas for Medical Sciences, Little Rock. This massive
$150 million hospital project - actually a replacement for
the existing hospital -- includes an 11-story patient tower,
a four-level underground parking deck and a five-story Psychiatric
Research Institute.
Half of the 11-story tower is built on grade and half is
built over the parking deck that will hold 1,000 cars, said
Keith Jacks, vice president and project executive of general
contractor CDI.
The patient care building contains 558,000 sq. ft., the psychiatric
building 100,000 sq. ft. and the reinforced concrete parking
deck 420,000 sq. ft., he said.
With space for 240 patient rooms, the hospital sits on a
drill pier foundation. "Because the parking deck goes
down 40 ft., we were already into rock," he said.
The hospital addition will consume 4,000 tons of steel and
43,000 cu. yds. of concrete. A heliport will sit atop the
tower.
The exterior will be a glass curtain wall and brick masonry
with accent composite metal panels.
Peabody Hill mixed-use dining hall,
Vanderbilt University, Nashville. The oval-shaped atrium
is open to all three floors and curved concrete stairs connecting
each floor are part of the structure of this $29.3 million
115,000-sq.-ft. building.
The atrium brings a couple of challenges, starting with scaffolding
that has to rise from the main floor to the roof, said Ed
Bullington, vice president and group manager at Hardaway,
the project's general contractor.
The other is the smoke evacuation system designed to work
in the open area.
The building has post-tensioned beams, and floors are conventional
slabs with rebar-reinforced concrete. The post-tensioned beams
can provide the same support with shallower beams, he said.
The exterior will be brick and limestone.
The roof will be covered by a TPO, or thermoplastic polyolefin,
membrane. TPO is said to combine attributes of EPDM and PVC
while qualifying as a "green" product.
The foundation is spread footings and isolated footings.
Westin Beale Street Hotel, Memphis.
Building a hotel for visiting NBA teams is like building other
hotels, with one exception. You have to raise the doors, the
room ceilings and showerheads by 1 ft.
That is how Flintco Inc. of Memphis is handling the top floor
of the $22 million Westin Beale Street Hotel, across from
the Fedex Arena in Memphis, home of the Memphis Grizzlies,
said Danny Moeschle, project manager. Rooms on lower floors
in the 203-room hotel have regular dimensions.
The nine-story building has post-tensioned concrete slabs,
held with 121,000 lbs. of steel cable. Another 650 tons of
rebar and 7,700 cu. yds. of concrete are going into the building.
The exterior includes a "signature" glass curtain
wall that slopes inward on one corner, along with brick veneer
and EIFS, he said.
|