|
Desiard Street deconstructed
Monroe street widening project
is resequenced midstream
By James Gordon
Though long overdue and highly anticipated, a road-widening
project in Monroe, La. had to be resquenced in the middle
of construction.
Timing the tasks according to their most suitable seasons
and redrawing the original engineering plans due to unaccounted
underground utility lines caused the project managers to reconfigure
the prescribed construction sequence.
Spokesmen for general contractor Merrick Construction Co.
of Cottonport, La., said the $13.5 million job that began
in May has an expected completion date in late October.
The project focuses on a 1.1-mi. section of U.S. Highway
80, or Desiard Street, that runs along the south side of the
University of Louisiana at Monroe's campus. The roadway is
being expanded from four to five lanes between its three-way
intersection with Gilbert Street at the east end and its five-way
intersection with Louisville Avenue (or U.S. Highway 165),
Powell Avenue and Sterlington Road on the west end.
The project was let for bid in December 2004 and Cain Merrick,
vice president and part owner of Merrick Construction, said
the contract it ultimately won was especially large for his
60-year-old company.
"Normally, when we do street-widening projects like
this, it is in the $4 million to $5 million range," Merrick
said.
Along with the fat contract came the two perennial difficulties
of tackling an urban street project of this magnitude: underground
utility lines and traffic management.
Merrick said the project was divided into two sequences.
The first to be completed was the widening of the roadway
east of Desiard Street's intersection with University Avenue,
which cuts through nearly at the halfway point of the project.
The second sequence required tearing out the existing roadway
west of University Avenue., laying 9 in. of class 2 base course
and laying 9 in. of concrete on top of that.
Also in the second sequence, a dangerous five-way intersection
at the west end of the project was to be reconfigured into
a four-way intersection, allowing Desiard Street to enter
Louisville Avenue at a 90-degree angle. Powell Avenue and
Sterlington Road were to be redirected to merge at only right
turns at the intersection.
The Desiard Street project also includes replacing the water
and sewer lines in the road as a part of a larger rehabilitation
of the water distribution system and sanitary sewer system
in the surrounding area.
Merrick subcontracted the water and sewer line work to JABAR
Corp. of Calhoun, La., which was to work ahead of the road
construction and install new water lines and meters on the
side of the road, where they would not be in the way of the
road construction. JABAR also had to replace the original
clay sewer lines with more durable polyethylene pipes.
But instead of working according to DOTD's original plans,
Merrick ended up working backward, doing sequence two before
completing sequence one.
John Eason, the DOTD project engineer who drew up the original
plans for the Desiard Street project, said that the switch
of the sequences was necessary because of a BellSouth fiber-optic
line that was not relocated before the project began and couldn't
be moved until a work order was issued.
That one line significantly delayed construction.
"This is an urban project," Eason said. "And
as with all urban projects, when you scratch the ground, everything
in the world is under there." There were also several
other fiber-optic lines that had to be avoided and 10 fuel
tanks that had to be relocated away from the path of the new
water lines.
"There is really not a lot of right-of-way to this job,"
Merrick said. "There have been real tight parameters."
With the approval of DOTD district construction supervisor
Marshall Hill, Merrick Construction was allowed to jump ahead
to other steps of the project. Hill also took over for Eason
as project engineer for several months and later reassigned
Eason back to the project.
The new sequence allowed Merrick Construction to do the toughest
part of the job first: tearing out and reconstructing the
road west of University Avenue. And the company was able to
work through the winter months because the weather permited
the pouring of concrete. The sequence also allowed them to
avoid higher traffic volumes while finishing the job.
"In the summer months, we are working sequence one from
University Avenue to the end of the job because it will go
a lot smoother," Merrick said. "The University of
Louisiana at Monroe is out of school for the summer, and there
is less traffic on that section."
While the construction did create a bottleneck, the traffic
flow was never stopped, said Ted Moulard, a project manager
for Merrick.
"We kept two lanes of traffic open all of the way,"
he added.
Now, Desiard has five lanes of traffic open from the new
four-way intersection to the intersection with University
Avenue. All of the asphalt has been laid, but Merrick Construction
still needs to apply the wearing course. Then the job will
be left to JABAR to re-head the manholes and bring the project
to its completion.
|