|
Old habits
Circa 1860 convent expanded, renovated
in Nashville
By Sam Barnes
During a $37.5 million expansion, 200-plus Catholic nuns,
many of whom had taken vows of solitude, were left with little
choice but to bend the rules and allow contractors onto their
cloistered Nashville campus.
The expansion would ultimately add 134,000 sq. ft. to the
convent with a new east wing and chapel, as well as renovate
the existing 146-year-old convent, which is operated by the
Dominican Sisters of St. Cecelia. The project was finished
this summer.
To keep contractors from working near the nuns, the owner
formed a three-person liaison committee to communicate its
objectives and coordinate scheduling with design-build contractor
Hardaway Construction of Nashville.
Trey Lee, senior project manager with Hardaway, was involved
in the project from the beginning of the design phase.
"We gave the owner about six different architects to
choose from, with oversight provided by our in-house design-build
staff," Lee said. The owner eventually chose Fowlkes
& Associates Architects of Nashville, which operated under
the supervision of Hardaway.
"In the early going we did surveys and took a lot of
measurements because there were no plans available of the
existing structure," Lee said. "Then we got into
a space-planning phase, where we had to observe them to get
a feel for their daily religious life and how it revolves
around the chapel and the building.
"It took a while for them to understand that men had
to be in the building," he added. "This convent
is essentially cut off from the outside world, and it's been
that way for more than 100 years."
Lee said it took a month or two of coaxing to get the older
nuns to understand what they had to do.
"They would have to announce that we would be in the
building and we could only go at certain times," he said.
"I met with a group of sisters once a week and they acted
as the construction liaisons. One was the lead, and they made
decisions by committee. It worked slow, but well. Once they
made a decision they stuck with it."
One of the nuns' unique design requirements was the construction
of 12-ft.-wide hallways, instead of the typical 8 ft. The
width was required throughout all new structures and the existing
convent to allow for the passage of several nuns without the
risk of contact.
"The initial phase, for the construction of the east
wing, began in 2003," Lee said. "At 120,000 sq.
ft., the east wing is by far the larger of the two new structures."
The four-story east wing sits on caissons and is a concrete
structure with cast-in-place, post-tensioned elevated slabs.
Slabs measuring 8 in. thick were necessary to accommodate
the column spans needed for the wide hallways.
The exterior skin of the east wing is made of brick, precast
concrete and windows, all of which match the skin of the existing
convent. Now complete, the wing houses a dining hall and kitchen,
infirmary, library and 99 living-quarter "cells."
At the same time, the contractor had to lay the groundwork
for the campus' new infrastructure, since virtually nothing
was up to code.
"We built a central powerhouse because the electrical,
fire sprinkler, mechanical and plumbing had to accommodate
the entire campus," Lee said. "As we brought in
additional things during future phases, we just tied into
it."
Construction of the 14,000-sq.-ft. chapel during phase two
began while the east wing was still under construction. The
chapel rests on a caisson foundation and has a structural
steel frame and steel trusses to support 42-ft. ceiling heights.
"The steel columns are 10 in. diameter and 40 ft. tall,"
Lee said.
After the east wing was completed, the nuns moved into the
new wing to allow the contractor to begin renovating the convent.
While working in the convent, the contractor encountered
severely outdated mechanical and electrical systems dating
back to the 1930s and 1940s.
"Put simply, the electrical system was a 'knob and tube'
configuration, which was common during the very beginnings
of electrical power," Lee said. "There was also
no air conditioning system and no fire alarm or fire sprinkler."
The heating system consisted of a boiler installed in 1950s.
"So essentially they were living in a wood structure
with no fire alarm and an antiquated electrical system,"
Lee said. "Add to that a lot of corridors with dead ends
and you have a codes nightmare."
During the renovation, the contractor added HVAC throughout
the structure (with a drop ceiling made possible by the existing
14-ft. ceiling heights), new electrical wiring, fire sprinkler
system and a new stairwell for life safety. Workers also closed
in some of the existing stairwells and completely gutted and
rebuilt all of the bathrooms, added new paint and floors and
refinished existing hardwood floors.
"On the lower floors we added guest sleeping quarters
and completely upgraded existing cells, changed out windows
and put in insulated historically designed windows to match
existing windows," Lee said.
In some locations, the crews had to replace deteriorated
brick walls - consisting of brick stacked several layers thick
- with steel columns and beams.
"In one area on the north side of the building, next
to an existing elevator, water had washed the mortar away,"
Lee said. "We essentially shored up all the floors from
the ground up and took out small sections of brick at a time.
We also cut in new door openings in some locations, so we'd
have to add columns and re-support the brick."
Outside the existing structure, crews performed cleaning
and tuck-pointing of the brick.
Lee said some quick thinking was necessary about two months
before the original completion date.
"The nuns asked that the project be completed a month
early," he said. "They have internal elections for
replacing positions inside the convent in June and they requested
that the project be finished by that date. Until that point,
we were on track to finish in July."
To accomplish the task, the contractor had to get special
permission from the nuns to work on Sunday.
"We had to work seven days a week from that point on,"
Lee added.
|