|
More room for research
Jackson medical center erects Guyton
addition
By Mark Friedman
The University of Mississippi Medical Center in Jackson,
Miss., was running out of research space, and the space it
had didn't comply with research standards, said John Hall,
the university's associate vice chancellor for research.
"We looked at the cost of renovating and it turned out
to be more costly than building a new building," Hall
said.
In November, Flintco Cos. Inc. of Tulsa, Okla., began construction
of the 195,066-sq.-ft., $43.8 million Guyton Research Facility
addition.
The seven-story building, with basements, is expected to
be completed in May 2008, said Michael McDonald, project manager
for Flintco.
"(The university) had been planning to do this project
for a while," McDonald said.
The addition will be attached to the existing four-story
Guyton Laboratory and an existing four-story classroom building,
said Joe Stevens, an associate at Eley Associates/Architects
in Jackson, Miss., which worked on the project with Simmons
Associates Architects of Ridgeland, Miss.
The addition will connect to all four floors of both the
classroom building and the existing research facility.
"We had to match the existing floor elevations,"
Stevens said. "Connecting it to one existing building
is problem enough; connecting it to two is much more challenging."
To begin the project, Flintco removed about 40,000 cu. yds.
of dirt to build the subbasements, which were about 35 to
40 ft. deep. The dirt was hauled to a landfill about 2 or
3 mi. away.
From the floor of the subbasement, Flintco drilled 125 concrete
piers with reinforced steel that descended between 30 and
40 ft. The piers range from 16 to 60 in. diameter.
"The building is pretty much taking up the whole space
that we've got out there, so we had to put up a pretty elaborate
shoring system that will hold >> the banks back,"
McDonald said.
Until the 12-in.-thick, 4,000-psi concrete walls were built
in the subbasement, the existing building was exposed.
"That's where we see the most critical part of (building
it) is, because you're working in the mud and down in a big
deep hole," McDonald said. "So every time it rains
you've got a lot of beams and drill piers to get into
the ground while it's wet and muddy."
After the subbasement walls were built, they were waterproofed
and back fill was put behind them.
The construction crew also had to deal with Jackson's highly
unstable Yazoo Clay. The clay expands when wet and contracts
when dry.
The soil would have pushed on the building, McDonald said.
"So we put the building on cardboard boxes," he
said. "They're specially designed void-formed boxes.
We put four layers under the slab poured the concrete on top
of that."
Over time, the 4- to 6-in. of cardboard will get wet, sag
and deteriorate.
"And that leaves a void under that slab," McDonald
said. "So when that earth moves up, the clay has space
where it can move up in that void and can contract back down
as it dries. So it's not putting the pressures on (the building.)"
Under the beams, a 2-ft.-thick layer of foam was placed.
Once the basement is done "then the structure will go
up pretty quickly. Then we start bricking and putting store
fronts up and finishing it out from there," McDonald
said.
The concrete for the project comes from Delta Industries
Inc. of Jackson, Miss., which is about half a mile from the
site.
"They mix it at their batch plant and ship it straight
to us," McDonald said.
The building is a cast in place concrete structure.
"It's a pan job," McDonald said. "We'll take
rectangular type field pans, set them, and the gaps between
the pans will make the beams.
"So we pour the slab and the beam together in one pour,"
he said. The floors are 5-in.-thick, 4,000 psi concrete.
Getting the materials to the site isn't a problem for now,
McDonald said.
There might be some delay in getting supplies in the future
because of shortages tied to Hurricane Katrina repairs, but
currently the materials can be scheduled in advance to have
on site as needed.
The materials are stored in an adjacent parking lot to the
building.
Because it is working on a hospital campus, Flintco needed
to be aware of the noise it was making.
"The noise and vibrations are big issues with a research
(lab on site)," McDonald said. "Any vibrations could
effect their operations."
When necessary, Flintco will begin a slab pour job early
in the morning to reduce the noise and vibrations.
Phase one of the project calls for building out the first
five floors of the structure. Phase two will build out the
remaining three floors.
Stevens said he didn't know when phase two would start.
The subbasement will house the mechanical equipment. And
the basement will hold the animals for research.
The first through fourth floors will be research labs and
part of the space will be used for the physiology research
and another area will be the Cardiovascular Center.
The skin of the building will be glass, brick and precast
stone to match the existing buildings on the campus.
"It's going to be a state-of-the-art building for research,"
Hall said.
"It's going to really give us the opportunity to grow
the research program at UMC and will be an attractive feature
as we try to recruit top name researchers from outside the
state to the university."
He added that the new building also will help the university
retain its researchers.
"Space is an important priority for researchers, and
this is certainly going to give us the opportunity to be competitive
at least with our surrounding neighbors in the research arena,"
Hall said.
Useful Sources:
For more information about the Guyton facility, go to: http://www.umc.edu/information/physical_plant.html
|