|
Condo rising
Little Rock gets 17-story downtown
high rise
By Mark Friedman
When the 17-story 300 Third Tower condominium building opens
in downtown Little Rock in April, it will be the third such
structure to open since 2002. And the city's condo craze doesn't
seem to be slowing down.
Little Rock's Moses Tucker Real Estate Inc. helped develop
the $29 million 300 Third Tower because of the demand for
condos, said Moses Tucker Partner Jimmy Moses.
"We think (demand) is very strong based on our sales
at 300 Third," Moses said. "We don't see much of
it slowing down right now."
The 300,000-sq.-ft tower will house retail space on the first
floor, a parking deck with room for about 180 vehicles on
levels two through four and 98 condo units on floors five
though 17.
The number of condos may wind up being 95 units because a
few owners are combining spaces, Moses said. The condos will
range in price from $235,000 to about $1 million and range
in size from 830 to 3,000 sq. ft.
When contractors East-Harding Inc. of Little Rock and Hensel
Phelps Construction Co. of Greeley, Colo., broke ground in
October, they had to deal with unexpected unsuitable soil
beneath an existing three-story building that was razed, said
Jay Herzing, project superintendent for the project.
"Under an existing building, you'd think it would have
some kind of decent dirt," he said.
Anywhere from 2 to 10 ft. of dirt, which was about 5,000
cu. yds., had to be removed and replaced with 5,000 cu. yds.
of clay, Herzing said.
The site became crowded with the removal of dirt and the
drilling of cement piers going on concurrently, said Hensel
Phelps project manager Charlie Barnard.
The piers went into the ground about 30 ft. deep and ranged
in size from 24 to 96 in. diameter.
The site for the tower is less than an acre in size.
"Scheduling and delivery were very important,"
Barnard said. "All the rebar is fabricated off site and
then it's tied on site. There's not much room for lay down
space."
Each floor of the parking deck is 30,000 sq. ft., while the
tower footprint is only 14,000 sq. ft.
The parking deck floors needed to be larger than the tower
to handle the cars, said Rick Redden, president of AMR Architects
Inc. of Little Rock, Ark.
"We put a top on the parking deck so you wouldn't be
looking down on the cars," Redden said. "On the
fifth floor, all of those units have a larger terrace."
On the west side of the building, the parking deck extends
75 ft., while on the east side it extends 45 ft.
Redden said there will be some landscaping on top of the
parking deck.
On the ground, construction workers don't have access to
the site from two directions because it borders a freeway
onramp and a city street. The city of Little Rock closed the
street in front of the project for a 252 ft. tall crane, which
is used for all of the project's vertical hoisting, Herzing
said.
"We've got the tower crane right off the street and
that allows us to bring in deliveries under it," Barnard
said.
Each cement floor of the tower is 8 in. thick and requires
4,000 psi concrete.
It took roughly 30 hours before the contractors reached 75
percent compaction on the cast-in-place concrete decks, Herzing
said.
"At 75 percent, we were able to stress the decks and
continue on," he said. "It's a typical site sequence."
In the center of the tower is the elevator shaft, which will
hold three elevators.
The largest part of the exterior façade will be glass
to give residents an unimpeded view of the city and the Arkansas
River, Redden said.
At the base of the building will be stone.
"We wanted (the building) to be warm in appearance because
sometimes concrete and glass can appear cold," Redding
said.
The building also will be decorated with copper and zinc
shingles.
The ground floor will hold the mechanical and electrical
rooms along with storage and retail space.
Moses said a hair solon has signed a lease and other leases
are pending for a grocery story and a bistro.
On the roof will be a 900-sq.-ft. lounge for the owners and
a sun deck.
|