|
The clock is ticking
Vols stadium project to be finished
by home opener
By Candy McCampbell
The clock is running on Johnson & Galyon Inc. of Knoxville,
which has four jobs under way at the University of Tennessee's
Neyland Stadium and a short timeline to finish them.
Work on the $24 million in projects began after the football
season ended in December and will be completed for the Vols'
season opener Sept. 2.
In fact, Bill Gardner, project manager for Johnson &
Galyon, general contractor on the project, is eyeing an early
August completion.
"We worked seven days a week for a while," he said.
Six-day weeks are now the norm.
The contract calls for:
- Construction of a new club level with more than 400 seats.
- Widening of concourses on the north and east sides.
- Building new restrooms and concession stands on the concourses.
- A major update of the utilities infrastructure.
The work is part of a long-term, $110 million stadium renovation
that also will add more elevators, change entry ramps and
install a new brick façade to give the stadium exterior
the same look as existing buildings on the Knoxville campus.
With the tight timeline, the project has run along several critical
paths, including demolition of needed areas and erecting 658
tons of new steel, Gardner said.
"Every piece of steel had to be field-measured,"
Gardner said.
The measuring took time but paid off later, said Ed McDougle,
principal at Ross Bryan Associates Inc., a Nashville consulting
engineering firm that is a joint venture design team partner
with McCarty Holsaple McCarty Inc., a Knoxville architectural
firm.
"The work has been performed in many stages," McDougle
said.
The club level is sandwiched between the upper deck and skyboxes
on the east side. The deck was strengthened in 2001 to handle
the extra weight with the addition of the skyboxes. The Ross
Bryan team got the drawings and checked the new, projected
loads on a computer model.
"The new columns of the upper deck had enough capacity,"
McDougle said. "That was the easy part."
A few cutaways in the skybox exterior panels allowed access
to the steel frame so support braces could be added under
the skyboxes.
"We had not originally planned to create computer models
of the old structure, but we had to bite the bullet (since
old drawings could not be located)," he said. In fact,
about 40 percent of the stadium is now on the firm's computers.
"We had to make sure the beams and column sizes matched"
and spent several days getting the measurements, McDougle
added. "It has gone together with fewer problems than
some new jobs."
The four rows of club seating, with 414 seats, are replacing
13 rows of stadium seating with 1,704 seats. The renovation
will cut stadium seating capacity from 104,079 to about 101,000
when complete, though the final seat count for the entire
project has not yet been set, said Scott Webb, architect and
construction administrator at McCarty Holsaple McCarty.
The new club seats, with a $25,000 one-time fee and a $4,000
annual fee, will help fund the renovation. The seats are all
outdoors and are protected by an aluminum "eyebrow"
roof stretching the length of the 240-ft. club level.
Behind the seats are large, open rooms for food service,
televisions and seating, protected by full-length glass walls.
The back is floor-to-ceiling, 1-in.-thick double-pane windows
overlooking the Tennessee River "to provide a view and
to continue the overall design vocabulary established by the
skyboxes above," Webb said.
Demolition work was critical from both time and space standpoints,
Gardner said. The old steel had to be exposed so new steel
could be added, and getting to the steel required the use
of small lifts, scaffolding and knuckle booms, he added.
A massive scaffold, constructed on the back side of the skyboxes,
hangs out over Estabrook Hall, a classroom building, so it
was covered with fabric sides to prevent material from falling
below.
"We had to be aware of the students at all times,"
Gardner said. Classes for the more than 26,000 UT-Knoxville
students have been in session during most of the time since
the job started.
A pair of stair towers that came down had to be ripped out
from the inside and braced from the inside, Gardner said.
Steel was hauled up with a crane and some building materials
were loaded on to existing elevators to get to the new club
level.
Concrete, however, was pumped up in two stages: to a bin
on the concourse, then through a 2-in.-diameter pipe to the
club level and a 3-in. pipe over the form to the club seats.
The job took about 1,000 cu. yds. of concrete.
Down below, parts of concourses on the east and north sides
are being enlarged from 30 to 90 ft. wide. This larger "pad"
also holds the new, bigger concrete block restrooms and expanded
concession stands.
More than 36,000 special-color and -shaped architectural
block and more than 40,000 regular CMU block are being used,
according to Ed Goan with Shoun-Allen Masonry Inc. of Morristown,
Tenn.
Included in the "below decks" area is a new concrete
block building housing the stadium's JumboTron electronic
controls.
Utilities to serve the 75-year-old stadium are also being
upgraded.
Almost 500,000 ft., or 94 mi., of power and low-voltage cable
and 200,000 ft., or 38 mi., of conduit are being added, said
Tony Stanley, project manager for Advent Electric Inc. of
Knoxville.
The electrical improvements involved some 24-hour electrical
shutdowns involving 10 other buildings, which had to be planned
and coordinated with temporary provisions for alternate power,
Gardner said.
The water lines to the main feeder just outside the stadium
are being increased from 4-in. to 6-in. diameter.
Laydown space is virtually nonexistent because the stadium
is surrounded by other buildings, so deliveries are on an
as-needed basis.
|