|
Southwest Louisiana Report
Post-hurricane growth spreads across
region
By Karla Wall
The southwest region of Louisiana is enjoying the sort of
growth normally experienced after a natural diaster such as
Hurricane Rita, said Loren Scott of Loren Scott and Associates,
co-author of the annual Louisiana Economic Outlook.
"There has been an increase in construction activity
due to new building and repair work and an infusion of insurance
money into the area," Scott said. Department of Labor
statistics show employment in natural resources and construction
is up 33.3 percent. In late August, the construction sector
in the region employed 10,100.
"Now, that number is 13,600," he added. "That's
a very significant jump in the sector and that's what's driving
the growth rate in the region."
The private sector will continue to experience steady growth
in the building, highway and utility construction industry,
said Scott Hines, Lafayette District area manager for Louisiana
Associated General Contractors.
"The private sector shows no signs of slowing down and
local municipalities will continue to press forward in putting
bond issues on the ballots for voters to decide, mainly as
an attempt to play catchup in addressing overstressed infrastructure
systems," Hines said.
A major catalyst for growth in the area will be the Gulf
Opportunity Zone Act (GO-Zone), Hines said. The legislation
is expected to generate roughly $7.9 billion in economic impact
in the state. "The program will provide a mechanism for
private businesses and corporations in the state to finance
construction and reconstruction projects through the issuance
of tax-exempt bonds," Hines said.
The residential construction sector in the region is booming,
said Henry Florsheim, vice president of the Lafayette Economic
Development Association. Florsheim pointed to the construction
of a new six-story apartment complex in downtown Lafayette
as an example and the development of Sugar Mill Pond near
Youngsville. Developed by the same group behind River Ranch
Community in Lafayette, Florsheim said.
In the commercial sector, the region should experience an
increase in small to medium oil and gas industry service businesses
and there's been an increasing interest in the construction
of warehouse/distribution centers, since Lafayette is situated
between the hurricane-damaged areas of Lake Charles and New
Orleans.
Driving the construction industry in Lake Charles are several
major industrial projects, including several planned LNG facilities,
each valued at between $600 million to $800 million.
Sempra Inc. will invest 250,000 man hours at its Hackberry
LNG facilty, said Ellis Benkenstein, Southwest region director
for Associated Builders and Contractors. Construction of a
$1.3 billion cogeneration plant facility at Citgo's Lake Charles
refinery will also boost the area's economy, Scott said.
Benkenstein also points to a possible expansion of the Calcasieu
Refinery in Lake Charles, as well as smaller projects at Conoco-Phillips
and Louisiana Pigment.
While there's more than enough work to go around, the fly
in the ointment may be the lack of qualified workers to help
complete it. While Hurricane Rita provided an increased workload,
it also meant a loss of workers as people who evacuated decided
not to return. And for a variety of other reasons, the industry
is facing a serious shortage of workers.
"We just don't have the manpower down here that we need,"
Benkenstein said.
"There's also a shortage of professional engineers from
all disciplines," said Hal McMillian, Calcasieu Parish
Police Jury member and head of business development for Levingston
Engineers in Sulphur. "We also need drafters and sketchers."
To address the problem, ABC is working with contractors and
construction leaders in New Orleans and Lake Charles, State
Dept. of Education officials, the Board of Elementary and
Secondary Education (BESE) and the state board of colleges
and universities to form a workforce commission group. Already,
43 community colleges in the state have adopted the same construction
training curriculum taught by ABC at its school. Benkenstein
said BESE has already implemented the same curriculum for
high school students.
McMillian said the recent development of the FEMA trailer
park in Lake Charles will ease the area's housing shortage,
which will allow the workforce to increase.
Other projects to watch include:
- Women and Children's Hospital expansion, $12 million
- Bridge improvement projects, Lake Charles/Kinder/Fenton,
$20 million
- I-49 contraflow lane, Lafayette, $3.5 million
- Stirling Ventures retail outlet, Lafayette, $20 million
- Hilton Homewood Suites (proposed), Lafayette, $20 million
Following are a few noteworthy projects currently under construction:
Ambassador Caffery Wastewater
Treatment Facility Upgrade. This $23 million upgrade
project, begun in June 2005, will boost the capacity of the
treatment facility from 6 mgd to 9.25 mgd, and will improve
odor control, said Kirby Stumpf of M.R. Pittman, primary contractor
for the project. The project will allow the facility to better
accomodate an increasing demand from a growing population.
The upgrade includes installation of a three-cell equalization
basin with a capacity of 7 million gallons. The concrete basin
is 25 ft. tall with 2-ft., 3-in.-thick walls and was poured
using 9,500 cu. yds. of 4,000-psi concrete. The project also
calls for the installation of two 2,700-gpm pumps and two
3,000-gpm pumps as well as a new four-celled sequencing batch
reactor unit with a 12-in. discharge blower that will increase
odor control for the facility.
A new secondary chlorine contact chamber is also being installed.
A new control center, fed by two distribution centers, will
allow remote control of power and communication throughout
the facility.
North Generation Project, Lafayette.
This two-phase project, involving the North and South
power plants, is being handled by TIC of Lafayette. The $40.9
million project began in July 2004 with the upgrade to the
8-acre North Plant, said project engineer Randy Stephenson
of TIC. The North Plant was completed in August 2005. Upgrade
to the 5-acre South Plant will be completed by in mid-June.
The work at each plant calls for the installation of two
CTG gas-powered peaking units designed to offset the normal
power supply. The units, 30 ft. wide by 90 ft. long by 40
ft. high, consist of a jet engine, hydraulic systems and a
generator. The unit is housed in .75-in.-thick steel plate
and the turbine is enclosed in a sound-proofed housing with
a 3-in.-thick layer of closed cell polyeurethane foam. A retention
pond, with a capacity of 40,000 cu. ft. of water, was also
installed at each plant.
The project will boost the capacity of the two plants from
500 mw to 700 mw, Stephenson said.
Sulphur Wastewater Treatment Facility
Upgrade. McInnis Brothers Construction of Minden is
spearheading this $18.6 million expansion to the Sulphur Wastewater
Treatment Facility. The project was begun in May 2005 and
is scheduled for completion by the end of the year, said project
manager Sam Bethea. Project engineer Wayne Harris with Meyer
Associates said the project will boost the plant's capacity
by 50 percent, raising peak flow from 18 mgd to 27 mgd.
Roughly half of the plant's existing equipment, most of which
is at least 20 years old, is being removed and the process
is converted, Bethea said. A four-cell sequencing batch reactor
is being added. Roughly 11,000 cu. yds. of 4,000-psi concrete
are being used for the 400-ft.-long, 200-ft.-wide, 25-ft.
deep unit. A 33-ft. deep lift station is also being added,
constructed of 750 cu. yds. of 4,000-psi concrete.
A new headworks structure is also being added to screen out
solids using a rotary drum screen. A 72-ft. by 34-ft. blower
building is being built, constructed of 12-in. heavy-duty
CMU, and a 2,800-kw generator is being installed for backup
power. Two 20-hp floating aerators will prevent the water
from becoming septic, Bethea said.
One challenge to the project has been the construction of
the SBR walls, Bethea said. The walls are battered, tapering
up from 2 ft., 3 in. thick at the bottom to 12 in. thick at
the top.
"The walls are tilted inward to make it more resistant
to overturn," Bethea said. Some of the walls are battered
on both faces and some only on one face. "The challenge
has been dealing with the complex intersection angles,"
Bethea said.
Critical Care Hospital, Franklin.
Woodrow Wilson Construction in Baton Rouge began work
on this $11.7 million project in November 2005 and project
manager Greg Rome said work will be completed by April 2007.
The 64,000-sq.-ft., one-story hospital will include an ER
unit, 26 patient beds, a respiratory care unit, surgical and
imaging suites and administration offices. The new hospital
will replace the older, larger hospital, which will be rented
out for commercial space, Rome said.
Roughly 45,000 cu. yds. of dirt were brought in for the project
from a borrow pit in Franklin. The fill was necessary since
new FEMA flood plain regulations required an extra 8 in. of
height in the footprint.
Oriented Strand Board Plant, Oakdale.
Martco Ltd., a division of Roy O. Martin Lumber Co. LLC, will
begin production at its new $210 million facility in October.
Work began on the project in May 2005.
The 210-acre plant will be, for a time, the largest facility
of its type in the U.S., said Adrian Schoonover, Martco vice
president of engineering.
"There are a couple of plants under construction that
will be larger once they're in operation," Schoonover
said. The plant will house about a dozen buildings, including
a 14-acre warehouse, a 5-acre process building and a storage
area for about 250 truckloads of pine thinnings per day.
Schoonover said the thinnings will be cut into flakes, dried
using three rotary heated-air dryers, coated with resin, layered
into different directions for strength and pressed together
with a press made of 5 million pounds of steel.
The process will be powered by the heated air produced when
the bark from the thinnings is burned in two heated energy
units, each capable of producing 215 million BTUs.
Schoonover said the plant will also have electrical power
supplied by Beauregard Electric for other operations.
I-10 Widening, Coone Gully to
Hwy. 27. Despite delays caused by Hurricanes Katrina
and Rita last year, this $42.4 million project to widen a
10-mi. stretch of Interstate 10 just west of Sulphur is moving
at a brisk pace, with crews working around the clock. The
project is expected to be complete by this fall.
The project will add a 12-ft. lane and a 10-ft. shoulder
to each side of the interstate, said project manager Marc
Dinnat with Diamond B Construction. The project also calls
for the widening of four bridges. Subcontractor for the bridge
work is T. L. Wallace Construction Inc. of Columbia, Miss.
Increased traffic flow, caused by emergency workers and evacuees
from the hurricanes, has been a problem, Dinnat said. Concrete
barriers have been placed to leave two lanes open for traffic.
Camelot of Broussard Nursing Home/Assisted
Living Facility. This $13 million new construction
in Broussard will house nine buildings for a total of 135,000
sq. ft. The Lemoine Co. LLC of Lafayette began construction
on the project in June 2005 and the facility is expected to
be completed by this month.
The facility will consist of an apartment-style assisted
living area, a traditional nursing home unit, an Alzheimer's
unit and a behavioral health unit as well as centralized kitchen
and dining areas.
State regulations have forced a fairly tight schedule for
the project, Wesley said. Vertical construction had to begin
by October 2005 to avoid a state-mandated moratorium on new
nursing home facilities. High material prices have also hampered
progress somewhat, Wesley said.
Louisiana Immersive Technologies
Enterprise, Lafayette. Acadiana will soon be home to
cutting-edge technology when this new $27.5 million facility
opens this summer. The facility will utilize two supercomputers
that run 3-D software to provide advanced visualization technology.
The facility will consist of four rooms, one of which is
a 3-D cave, or immersion auditorium, said Robert Billeaud,
president of J.B. Mouton of Lafayette, primary contractor
for the project. It will also include a 50,000-sq.-ft. office
rental space, an auditorium with a seating capacity of 175
and a 37-ft. 3-D screen, and a conference room.
The 80-ft., 3-story glass dome will have six projectors which
will display images on the walls, floors and ceiling. The
effect will be a 3-D representation that can put users in
virtually any environment. The technology will have nearly
unlimited applications and will attract a wide variety of
businesses and industries.
The project, a joint venture between ULL, the Lafayette Economic
Development Association and the state, was bid in a unique
way.
"Public work in Lousiana, by law, can be bid on by any
company," Billeaud said. "This project was bid by
invitation-only. There were three bidders. LEDA was able to
bring the spirit of cooperation that is normally found in
a private sector bidding process and make it work in a public
project."
|