|
Hybrid garage
Opelousas, La., hospital relies
on diverse concrete applications
By Karla Wall
The Lemoine Co. LLC of Lafayette, La., recently completed
construction of a five-story hybrid concrete parking garage
for Opelousas General Hospital in Opelousas, La. Work started
on the project in August.
The garage is part of an expansion project that includes
a six-story hospital tower, which will house a new ER/Trauma
admitting area, a cardiovascular suite, two physician's suites,
and a critical-care unit. Work on the project was completed
in mid-May.
The garage, situated on a 240- by 124-ft. footprint, is built
on roughly 200 4,000-psi auger-cast concrete piles sunk to
depths of 55 to 70 ft., said Tim Burdette, project manager
with Lemoine. The piles are 16 in. diameter and are reinforced
with steel bars tied into pile caps.
The pile caps cover anywhere from one to six piles, Burdette
added.
The 24,000-sq.-ft. foundation deck is reinforced with 150
tons of steel reinforcement, said Scott Anderson of Keystone/Stewart
in Houston, which did the foundation work for the garage.
Roughly 2,000 cu. yds. of 3,000-psi poured-in-place concrete
was used for the foundation, Anderson said.
The ramp leading up to the first parking level is constructed
of 4,000-psi cast-in-place concrete. Fill dirt was brought
in for the ramp foundation and was shored up with steel panels.
The elevated decks were constructed of roughly 2,800 cu.
yds. of 5,000-psi poured-in-place concrete, said James Sweetin
of Tulsa (Okla.) Dinastan, subcontractors for the parking
garage construction. He added that 4,700 cu. yds. of 5,000-psi
precast was used for columns, girders and beams.
Columns are roughly 2 by 2 ft., said Burdette. Upper decks
are reinforced with post-tensioned slabs, and the precast
columns, girders and beams are pre-stressed.
Two stairwells leading from the first through fifth floors
are situated at the east and west ends of the garage. The
stairwells consist of steel pan stairs infilled with 3,000-psi
concrete. A hydraulic elevator is located at the west end
of the garage. The elevator shaft is constructed of 8-in.
concrete masonry unit blocks.
A 30- to 40-ft. connecting bridge between the garage and
the new hospital tower is situated on the first floor. The
bridge is constructed of 3,000-psi poured-in-place concrete
and built on slab-on-grade.
Weather delays were a problem on the site, Sweetin said.
Work was delayed roughly two weeks due to rain. There was
also a mid-stream change of scope which required the addition
of a sixth floor to the tower.
"The fifth floor was to be built with the possible addition
of a sixth floor in mind," Burdette said. "They
decided to go ahead and add the sixth floor, and we had to
truncate the schedule somewhat to accommodate the change.
We also had to make sure the elevator construction was completed
in order to carry materials up for the sixth floor construction."
Poured-in-place concrete was supplied by Angelle Concrete
of Lake Charles, La., Keystone Concrete/Stewart Builders of
Houston, and Cajun Constructors of Baton Rouge, La. Precast
was supplied and installed by Tulsa Dinastan.
|