|
Industry report
Concrete gains popularity after
bump in steel prices
By Candy McCampbell
Concrete is being used more in all types of construction
- 455.9 million cu. yds. was used last year in the United
States, which is 6 percent more than in 2004, according to
the National Ready Mixed Concrete Association.
And look for another 3 percent increase this year.
Lionel Lemay, NRCMA vice president of technical resources,
said growth will come in part from the use of innovative applications
of concrete, such as insulating concrete forms and pervious
concrete.
Pervious concrete allows water through its surface and is
gaining popularity for parking lots, especially where runoff
or ground water is an issue.
"That's going to be the next big thing for our industry,"
Lemay said.
Concrete is the material of choice for many buildings, primarily
because of economics, said Mike Tibbett, manager of the concrete
and heavy civil division of Hoar Construction in Birmingham.
Concrete is more readily available, can be enhanced with
chemical additives and can be used in buildings where vibration
must be minimal, he said.
Al Gogolin, structural engineer at Skanska Building USA in
Atlanta, said concrete is generally faster, more fire resistant
and allows for a more compact floor depth.
"That may be a few inches per floor, but on a 30-story
building it adds up to a real cost factor," he said.
Other factors prompting an increase in concrete use include
sharp steel price increases and the greater use of concrete
in housing construction.
Following are a few significant concrete projects across
the south central region:
Baptist Memorial Hospital 11-Story
Patient Bed Tower, Southaven, Miss. The $177 million
building, in the New Madrid Fault area, is being constructed
under the 2000 International Building Code, so it is structurally
designed like a hospital in earthquake-prone California.
It has 20-30 percent more reinforcing steel than usual, using
about 5,300 tons, said Paul Moffat, project executive with
general contractor Bovis Lend Lease of Nashville.
The 450,000-sq.-ft. building is made of 3,100 cu. yds. of
concrete, with shear walls that are 12 to 14 in. thick, he
said.
The building sits on 20-in.-diameter piles, auger drilled
55 ft. to as much as 80 ft. for the main building, Moffat
said.
The hospital design put major loads like CT scanners and
MRI machines on the ground floor, where the slab on grade
is 6 to 8 in. deep instead of the usual 4.5 in.
It was only wind that slowed the earthquake-resistant building
last fall. High winds halted installation of precast concrete
panels for about 20 days, Moffat said.
The exterior is made of decorative stone, brick and precast
concrete panels.
Vanderbilt University Medical
Research Building 4, Nashville. This $120 million post-tensioned
concrete structure is an example of how finely tuned a 12-story,
420,000-sq.-ft. project can be.
It joins two existing buildings - one of them an auditorium
- and expands upward to create additional laboratories, classrooms
and offices.
Central to the project is the support from four post-tensioned,
cast-in-place concrete trusses to go over Langford Auditorium,
an existing four-story building.
The truss system is massive - each truss is 24 ft. tall,
140 ft. long, 5 ft. thick and requires 500 tons of concrete,
said Merrill Bowers, project manager with general contractor
Turner Universal Construction of Nashville.
Construction is taking longer than planned.
"The design process and interaction between the subcontract
engineers and engineer of record has involved much more redesign
than originally expected," Bowers said. Pouring of the
trusses started in late April and should be finished by mid
summer.
Other work has been progressing, such as floors and columns
for the west side, installation of some precast and glazing
and air chillers in the basement, Bowers said.
Jackson-Madison County Hospital,
New Patient Care Tower, Jackson, Tenn. The $117 million
nine-story tower is a "hybrid building" - the first
three stories are reinforced concrete and the top six are
structural steel, said Vince Bender, project manager with
Centex Construction of Nashville.
The tower, which adds more than 356,000 sq. ft., is located
between two existing patient tower buildings.
Excavation for the new tower would have exposed the footings
of the present towers and the sheet piling proposed to shore
them up would have caused too much vibration.
The answer: drilled shafts with permanent steel casing, placed
strategically so they could serve both as shoring for the
existing buildings and foundation for the new one, he said.
"By changing to a drilled pier system we were able to
save 10 days on the schedule and keep the vibrations to a
minimum," he added.
A tunnel links the emergency department, which is housed
in the new tower, to the Central Energy Plant and laundry,
he said.
Excavation for the tunnel, however, was next to the hospital
loading dock. Centex built a beam and lagging shoring system
so the tunnel could be built without interrupting operations
at the loading dock.
Guyton Research Building Addition,
University of Mississippi Medical Center, Jackson, Miss. This
$43.6 million 189,000-sq.-ft., seven-story, all-concrete building
doesn't sit on the clay dirt onsite.
It sits on cardboard boxes, said Mike McDonald, project manager
with general contractor Flintco Inc. of Memphis.
The repeated expansion and contraction of clay prohibits
structural contact, he said. "It has to sit on foam or
cardboard boxes."
The medical research building addition is built on a pan
joist concrete system and has additional beams to meet requirements
for minimal vibration in the laboratories, he said.
Two floors are underground, meaning "waterproofing is
very important," he said. Flintco used a roll-on material
to waterproof the structure, plus backfilled with sand and
a drain system.
About 1,600 cu. yds. of concrete will be used in the building,
which will have an exterior of brick, precast concrete panels
and glass. It ties into an existing four-story building.
McDonald has not had to worry about noise because there was
no rock on the site, which meant no blasting, but there is
no laydown space in the middle of the medical center so all
deliveries had to be "just in time."
Auburn University Transportation
Technology Center, Auburn, Ala. Before this $21 million
building could get out of the ground, it had to get out of
the water.
The finished basement floor was 8 ft. below the groundwater
level so it had to be redesigned, said Kelley Pennington,
vice president at general contractor Bailey-Harris Construction
of Auburn, Ala.
"We needed to take out the strip footings and redesign
the whole subdrainage system," he said.
The entire basement was sloped to one section so it would
drain into the subdrainage system, he said. The revision "took
months off the project," he added. The solution allowed
workers to make up the time lost.
"Had we not implemented the solution, we'd still be
there," Pennington said.
The 193,000-sq.-ft. building is constructed on pan slabs,
a process that "creates beams and joists within the slab
to accommodate reinforcing," he said.
The technique also allows elimination of unnecessary concrete,
an estimated one-third here, Pennington said.
Concrete is being used only in the slabs and basement walls.
Other walls are non-structural and made of concrete block.
One beam will be an ornate 60-in.-radius, cast-in-place concrete
stair that will require some complicated forms, he said. Plans
are to pour it all at once.
CCL Label Manufacturing Plant,
Collierville, Tenn. There's a pressing deadline for
this $12 million 111,000-sq.-ft. manufacturing/warehouse building.
Three large printing presses are to arrive from Germany in
early 2007 so the structure has to be ready then, said Michael
W. Brewer, executive vice president of general contractor
Linkous Construction Co. Inc. of Memphis.
The floor will be a conventional slab that will be thickened
to about 2 ft. deep in the press area, he said.
The tilt-up wall building is nothing new for Linkous; it
has built similar buildings for year. A typical panel here
will be 25 ft. wide and 30 ft. tall, the largest at 33 ft.
wide and 32 ft. tall.
About 7,000 cu. yds. of concrete will be needed and about
3 lbs. of reinforcing steel per square foot of wall, so each
panel will weigh 45 to 50 tons, Brewer said.
"The walls are insulated panels, with a layer of Styrofoam
inside two different pours," he said. They will be poured
onsite.
It takes about four weeks from time of pour to time of erection,
using a crawler-type crane. Add another four weeks to get
all the panels up, he said.
"Quicker, cheaper, that's the name of the game,"
Brewer said.
"You can pour faster and get a building up cheaper than
with precast or masonry." A building like this would
be up about four weeks faster, he said.
Westside Wastewater Treatment
Plant, Fayetteville, Ark. This $59.9 million project
is unusual because it is a completely new wastewater treatment
operation "from the ground up," said Tom Marcum,
project manager with Brasfield & Gorrie of Birmingham,
Ala.
"There was nothing there," he said. "The transmission
lines coming into the plant are being constructed as we speak."
The plant consists of 27 structures that will consume 30,000
cu. yds. of concrete, which Brasfield & Gorrie is placing.
Among the structures are an operations building; inlet facilities;
four biological units; four final clarifying tanks; storage
units and the other tanks; holders and filters that are used
to treat wastewater.
They will be connected by more than 13,000 ft. of iron pipe
that is 6 to 60 in. in diameter, he said. About 3,000 tons
of reinforcing steel will be needed.
The final clarifying tanks, about 110 ft. in diameter, will
have 15-in.-thick walls, he said. The oval-shaped biological
tanks are about the size of a football field, built in a series
that runs together.
The plant, which will use an ultraviolet disinfection system,
will remove all the water from the waste, leaving solids that
will be hauled off.
|