|
Lasting impression
Concrete hotel tops out next to
Shreveport, La., convention center
By Angelle Bergeron
Walton Construction Co. is hoping to make a lasting impression
on the City of Shreveport, La., with the construction of the
$34.3 million Convention Center Hotel. The Kansas City, Mo.-based
contractor has a reputation for hotel building, but this marks
the first for the company's Shreveport division.
Shreveport is likely to need more hotel rooms in the near
future, considering the January opening of the 350,000-sq.-ft.
Shreveport Convention Center. The Convention Center is the
second largest in the state and the largest in what is referred
to as the Ark-La-Tex tri-state area.
"Our relationship with the city is very important,"
said Tommy Clark, Walton's director of business development.
"We are doing everything we can to let the mayor cut
the ribbon before he goes out of office."
Walton began construction of the 12-story, 314 room hotel
in August. Poured-in-place, post-tensioned concrete and a
precast concrete skin comprise the 224, 747-sq.-ft. structure.
The project will be complete by the end of December.
In spite of numerous delays on the front end of the schedule,
the contractor is still planning a soft opening of 150 rooms
by mid-November, Clark said.
The first delay came when the contractor started to drive
pilings for the project.
"It was a cleared site and the owner thought everything
was out of the ground when we started construction, but that
wasn't the case," said Tony Brown, Walton superintendent.
"We hit foundations, old pipes, wire, anything you could
think of we found."
The original demolition and excavation contractor had to
be brought back in to reclear the site, which was formerly
a railroad station.
"They took out foundations, tree stumps, railroad ties
and tracks, all kinds of stuff out of the ground," Brown
said. Walton was certified to move forward when the contractor
ran into another obstacle.
"There was a main sewer pipe right in the middle of
the site that wasn't supposed to be there," Brown said.
"If we had started driving, we would have been in some
deep you know what."
Next, it was evident some design changes would be required
when Walton realized the contractor for the Convention Center
extended the pier caps for the adjacent building's foundation
2.5 ft. into the hotel's right-of-way.
"That made us have to use one-sided forms instead of
conventional forms and form our caps adjacent to their caps
by drilling into them and adding epoxy," Brown said.
However, that design change worked in the hotel's favor because
the contractor placed 18 in. of concrete in the transition
area, instead of the originally specified 13 in.
"The hotel is only 15 ft. from the Convention Center
on the west face and 8 ft. on the south face," Brown
said. "It makes it very difficult working that close,
and there is no lay-down area. We're building road to road
and building to building."
To speed up the schedule, the contractor is using two-day
break concrete, which allows workers to stress cables on the
second day and keep the forms moving up, Brown said. "We
do a floor every eight days," he added.
Dun-Par Engineered Form Co. provided table forming with scaffolding
for the project, which "makes it much faster than conventional
stick building," Brown said. Walton expects to top out
July 1.
The two-day, high-early mix is rather basic, but the contractor
is using a special mix design for the building's five elevator
cores.
"It's a self-leveling, pea gravel mix that achieves
5,500 psi in two days and cures out around 8,500," Brown
said.
The heavy-aggregate mix is necessary because the re-bar configuration
in the walls of the elevator cores doesn't allow enough space
for vibrators, said Richard Carter, quality control manager
for Texas Industries Inc.
The Dallas-based company's northwest division in Shreveport
is Walton's concrete supplier.
"This self-consolidating concrete is a relatively new
mix in this area," Carter said. Although most concrete
is tested by slump, this mix is tested by diameter, he added.
"You measure the diameter of the material as it is poured
out of the cone and we're trying to get a 26- to 28-in. diameter,"
Carter said.
The mix will achieve its compressive strength in two or three
days instead of the 28-day requirement, he said. Additionally,
because no vibrating is required, it decreases labor, which
has been a huge consideration on this project.
"In Shreveport, it seems like you have problems getting
labor because they are not geared up to doing big buildings,"
Brown said. "I think everything works here with the exception
of finding qualified help to keep up the schedule. We had
to bring a foreman and a couple good carpenters from Detroit."
In the wake of hurricanes Katrina and Rita, there was rampant
speculation about material and labor costs, so Walton anticipated
the problem and gathered what it would need to complete the
job.
"We anticipated the problem and jumped ahead,"
Clark said.
To catch up the lost time, the contractor worked seven days
a week, 20 hours a day through April. Although Walton has
not been restricted to working certain hours, the contractor
is "coordinating our efforts with Convention Center operators
to eliminate any headaches it may cause on any of their events,"
Clark said.
By the beginning of May, Walton had revved up to three shifts,
to accommodate CoreSlab of Oklahoma, which is manufacturing
and erecting the exterior, precast skin.
Useful Source:
A
live shot of the hotel jobsite
|