|
Preparing for growth
New I-12 interchange to alleviate
traffic congestion
By Angelle Bergeron
For the past 15 to 20 years, residents of Denham Springs,
La., have been waiting for a new Interstate-12 interchange
that would alleviate traffic in the popular Baton Rouge bedroom
community.
Since Hurricane Katrina precipitated a population explosion,
the opening of the Juban Road Interchange by the end of this
year will be even more welcome.
"The population has been growing for years and they've
been trying to get an additional entrance to the interstate
between Denham Springs and Walker, La.," said Clay Holloway,
project engineer for Louisiana DOTD. "Right now, there's
an overpass, but no interchange."
Denton-James Construction of Baton Rouge began work February
2005 on the $18.6 million contract to construct the interchange
and re-align a 1-mi. stretch of Juban Road leading up to the
interchange, said Roger Daughdrill, project manager. Denton-James
is re-aligning Juban Road, which is Louisiana Hwy. 1026, 800
ft. west of its current location so the contractor can install
the new intersection before the old overpass is removed. In
addition to providing on- and off-ramps to I-12, the interchange
will provide greater flow for LA 1026 because it will be four
lanes instead of two.
|
"Our target date is to be finished by September, which
would put us ahead of DOTD's November finish date," Daughdrill
said. Because DOTD suspended the contractor's work on some
holidays to expedite the flow of traffic, the contract will
likely be extended through the end of December, Holloway said.
Currently, Denton-James has only completed 43% of the work
although 53% of the time has elapsed, he added. With a $5,000
a day bonus/penalty, the contractor has plenty of incentive
to beat the deadline.
"Getting the initial embankment surcharge in and letting
it sit was the main objective and it just took a while to
get it there," Daughdrill said. "We had a lot of
wet weather last year." In order to achieve sufficient
compression, Denton-James placed a 3-ft. surcharge atop the
headers for the bridge and had to let it sit for 90 days.
Placing the surcharge to speed settlement is standard, but
this was the first time the DOTD specifications also required
the placement of vertical wick drains beneath the header on
the embankment.
"They placed the wick drains down 42 ft. into the ground
to make sure they could get all the water out," Holloway
said. The wick drains extend about 500 ft. north and south
of the bridge and about 20 ft. from the top of the embankment,
he added.
By the end of March, Denton-James began placing girders for
the overpass. "Although the traffic isn't too heavy on
1026, it is really heavy on I-12, so setting up the girders
has to be done at night," Daughdrill said. The contractor
is only allowed to stop traffic from 8 p.m. to 5 a.m. and
only for 20 minutes at a time.
"We expect more problems as we try and set up the girders
(in late March)," Daughdrill said. "We are only
allowed to stop the traffic for 20 minutes at a time to set
a girder and with heavier traffic it will take longer than
normal to wait until traffic clears so we can set another
one."
In order to move cranes onto the site, the contractor had
to stop traffic for 15 or 20 minutes, and then it took from
30 minutes to an hour before the normal flow returned, Holloway
said.
"Since the hurricane, it's been bad, but from 8 to 5
they should have enough to get the girders in."
The contractor is scheduling delivery of eight of the 100-ft.-long
AASHTO Type IV girders to be delivered each night.
"We don't have a laydown area, so we've got to take
them off the truck as they come in," Daughdrill said.
Each of the 82,000-pound girders must be loaded onto the
truck in a special direction and delivered in appropriate
placement order, said Max Williams, vice president of sales
at Gulf Coast Pre-Stress, the Pass Christian, Miss., company
producing the girders.
"The biggest challenge will be getting the types of
trucks with enough axles to transport them," Williams
said. "No one company keeps that many pieces of equipment
because you just don't use them, so we're having to round
them up."
Although Gulf Coast contracted with Denton-James to supply
the girders in December 2004, the company was hard hit by
Hurricane Katrina. An 18-ft. storm surge pushed through the
yard, destroying all of the company's raw materials, some
finished products and all of the shipping equipment, Williams
said. The six trucks Gulf Coast did have are either being
rebuilt or repaired. "All of our equipment went under
water," Williams said. "Some were totally lost and
some could be re-worked."
Still, the largest tax-paying company in Pass Christian managed
to rally, shipping out its first finished product a week after
the storm and pouring it first product on Sept. 30. Although
Gulf Coast is still replacing equipment that was corroded
by the saltwater, the company is working full speed to keep
up with the backlog created by ongoing projects like Juban
Road and reconstruction projects.
In addition to the 60, Type IV pre-stressed concrete pilings,
Gulf Coast will be providing Denton-James with 149, 14-in.
piles and 48, 18-in. piles.
Without question, the traffic is the biggest concern for
the contractor, as well as any subs scheduling deliveries.
It is likely to get worse before it gets better, especially
when Denton-James ties in the on- and off-ramps towards the
end of July or beginning of August.
"We are going to narrow the lanes and move them over
to tie in the off- and on-ramps, but that will be one of the
last phases of the job," Daughdrill said.
|