|
Speedy relocation
Steelscape brings California facility
to Shreveport
By Martin Schwartz
The need for speed has pushed the Steelscape Red River Project
at the Port of Shreveport-Bossier since the first phase of
the four-phase $200 million project broke ground in July.
Steelscape is relocating an existing facility from Richmond,
Calif., to Shreveport.
"They're taking everything apart and bringing it here,"
said Ryan Roberts, site project manager for the Wieland-Davco
Corp. of Lansing, Mich. "We had about six months to build
the building and they want to go into production a month after
it's finished. This is their main distribution for the east
coast. That's why it's such a fast-track deal."
Steelscape Inc., a subsidiary of Monterrey, Mexico-based
Grupo IMSA, is one of the only coated-steel producers in the
United States to process raw material from hot band to finished
product in its own facility. The four-phase construction project
is being built on a 75-acre site on the west bank of the Red
River.
The first phase required construction of the 225,000-sq.-ft.
paint line building, which was completed in February. The
pre-engineered metal building was built on the site of a former
cotton field.
"The cotton was about knee high when we got here so
we stripped it out," Roberts said. "The good thing
was that the site required no special treatment or environmental
work."
But the land was flat and the soil unsuitable, so contractors
hauled in fill dirt to create a building pad and raise the
site elevation.
"We had to build up the grade about 3 ft.," Roberts
said. "We brought in 22,000 cu. yds. just for the building
pads."
The foundation for phase one consists of 331 auger-cast piles
with pile caps >> and concrete grade beams with a separate
equipment foundation supported by 196 auger-cast piles. The
flooring is reinforced with a concrete mesh that will enhance
the long-term durability.
Roberts said AEPSWEPCO of Shreveport is running new electrical
lines to the site to provide power and Wieland-Davco is hooking
up equipment to a transformer transferred by Steelscape from
its California operation. All water, sewer and gas lines have
been provided by the Port of Shreveport-Bossier.
Steelscape is the 11th tenant to locate on the 2,000-acre
port. The location was vital to Steelscape's need to receive
raw materials and move its product out.
"Eighty percent of their product comes in by rail,"
Roberts said. "This has excellent rail access. They also
ship a little bit by barge and we're right here on the Red
River."
"We're delighted that Steelscape chose the Port of Shreveport-Bossier
to be its partner in progress," said Eric England, director
of the Port of Shreveport-Bossier. "It's a tremendous
opportunity for the region. Steelscape's presence will more
than double the traffic through the port and will represent
a $400 million impact to the region."
Phase two of the project began in January and consists of
a pre-engineered metal building to house the company's galvanizing/galvalume
line. Unlike the phase one building, phase two will have virtually
all new equipment. The foundation required 338 auger-cast
piles for the building, but Roberts was uncertain how many
would be needed for the equipment.
The phase two site required 14,000 cu. yds. of dirt to level
the ground for construction.
Roberts said seven subcontractors are working on the two
phases currently under construction, all locally based except
for L. G. Barcus, a Kansas City-based company that is installing
the auger-cast piles.
"We're working about 200 men a day," he added.
"I've got four of my own people here."
Wieland - Davco Corp. has performed three other projects
in the Shreveport-Bossier area - including work with General
Motors suppliers - so Roberts' team is familiar with the subs
being used on the project.
"It's a good group of people," Roberts added. "We
work all over the country, so we have a large subcontractor
pool that we can pull from, but we're real happy with the
labor here."
The architect on the Steelscape Red River Project is Kevin
Bryan, working for engineer-of-record Aillet Fenner Jolly
& McClelland Inc. Matt Wallace is the construction engineer
and Mark Snow is the civil engineer.
"On a project like this, the Steelscape project team
is the main driving force for the project," Roberts said.
"We have to work closely with them practically on an
hourly basis just because of the fast-track part of it. They
give us real good support to make sure we have all our pieces
and parts in the right places and they're there when we need
information."
The mild winter weather has helped the contractor maintain
the speed necessary to complete the project on time.
"Most people think of Louisiana as being wiped out by
the hurricanes," Roberts said. "When I'm talking
to people back home they ask, 'How can you get anything done
down there?' We've been very fortunate that it has been dry.
A farmer would be pulling his hair out over this weather,
but it has been a major contributing factor to the speed of
this project.
"We're right on schedule."
|