|
Inside looking out
Access ports to provide entry into bridge girders near
Nashville
By Candy McCampbell
Highway Department engineers in Tennessee will no longer
be on the outside looking in.
A bridge being built as part of a new $31 million, 2.8-mi.
section of Nashville's Vietnam Veterans Boulevard by Rogers
Group Inc. of Nashville will have access ports in its steel
cap girders so engineers can crawl inside for inspections.
The bridge's steel beams tie into the girders, which in turn
rest on the concrete columns.
Vietnam Veterans Boulevard, or State Road 386, runs from
Interstate 65 at Nashville's northern edge, bypasses Hendersonville
and will end near Gallatin. The current construction segment
runs from Saundersville Road to Station Camp Creek Road.
"The contract completion date is November 2006, but
we're scheduling it to finish in October 2006," said
Todd Nash, project manager for Rogers Group. Clearing started
in November 2003.
Gerald Guinn, executive vice president of steel erector
Sentry Steel Co. Inc. of Hendersonville, said the cap girders
weigh about 39 tons each and reach as long as 28 ft.
The 780-ft.-long steel girder bridge is the largest of six
in the boulevard extension and sits on concrete-filled steel,
6-ft.-wide metal cans sunk 12 to 38 ft. deep. The cans support
cap girders that are bolted to steel bridge girders, which
will carry traffic over a railroad track.
Nearby, a 740-ft.-long steel girder bridge stands on poured-in-place
concrete piers that support span lengths of 279 ft., 224 ft.
and 236 ft., Guinn said. The remaining bridges are made of
precast concrete beams over poured-in-place concrete substructures,
the longest stretching 265 ft.
D.W. "Red" Binkley, Sentry's general superintendent,
said the steel bridges will require the largest bolts ever
used on a Sentry project, measuring 13.5 in. long and 1 in.
diameter.
"We're using 29,000 (of the) 1-in. bolts," he said
Concrete caps must be positioned exactly right because fabricator
Vincennes Steel Corp. of Vincennes, Ind., has pre-assembled
the steel girders at a radius.
"They put the bridges together, 200 ft. to 300 ft. at
a time, to the right pitch and elevation," Guinn said.
The bridge girders are made of high-strength steel that develops
a thin layer of rust to self-protect the girders from additional
corrosion.
Laydown space is scarce.
"We take delivery as needed, and they go up within a
day of delivery," Nash said.
The bridge is topped with panels of metal decking laid by
crews from Gilley Construction Co. of Manchester, Tenn.
Gilley is also placing and tying 800 tons of epoxy-coated
rebar on this job, said Vicki Gilley, company president.
Guinn said all the bridges have concrete decks averaging
9 in. thick. The decks have more than 6,800 cu. yds. of Class
D concrete and the substructure has more than 5,000 cu. yd.
of Class A concrete.
"We got a lot of paving done in January," Guinn
said. "We had some good weather and took advantage of
that."
The project also has three box culverts, two for existing
streams and one to allow access for vehicles and cattle on
a farm that is bisected by the highway.
Work started on the bridges sooner than planned because the
site work was done quickly, Nash said.
"The subcontractor that did the grading, Wright Brothers,
did an excellent job in moving quickly, and allowed us to
start the bridges quicker," he added.
"This job consisted mainly of rock fill. With them being
able to get that volume of earth moved, it put us (ahead)
several months."
The project required moving a total of 377,874 cu. yds. of
material, 223,037 cu. yds. of which was rock. Some of the
rock came from a cut in a hillside and nothing had to be hauled
offsite.
"This is an all-rock job," said Tom Whitsitt, vice
president, chief engineer and estimator at Wright Brothers
Construction Co. Inc., of Charleston, Tenn. "There are
no seasons in an all-rock job, so that's one of the things
that helped" the site work finished early.
The road runs through open land, so Wright could use off-road
equipment instead of highway trucks to haul the rock.
Another break came when the Tennessee Department of Transportation
allowed Rogers to limit traffic to one lane for bridge erection,
Nash said.
"The specs allowed us to close on weekends, but it would
have been 10 to 14 weeks," Nash added. "We asked
TDOT to have one-lane traffic for 7 to 10 days, which cut
down on the amount of time."
The mayors of Hendersonville and Gallatin also were "very
receptive" to the more limited highway closing, he said.
CSX Railroad keeps a flagman on duty whenever road crews
are out so he can alert them of approaching trains and alert
engineers of the construction.
Utilities were taken care of early on, with Nashville Gas
Co. relocating gas lines and White House Utility District
moving water lines.
There is little drainage involved, because the shoulders
are designed for runoff, Nash said. Just under 6,000 ft. of
concrete pipe, ranging from 18 in. to 48 in., are being used.
Useful Source:
For more information about the project, go to: http://www.tdot.state.tn.us/
|