|
Saving time
Lanes added to Alabama stretch of I-20 under heavy traffic
By Sandra Bearden
A job must finish on time, so John Brown of Good Hope Construction
Inc. of Cullman, Ala., paid attention when a subcontractor
said it could shave time off an essential step in the $25.6
million widening of Interstate 20 between Pell City and Riverside,
Ala.
"Sherman Dixie Concrete Industries proposed we use precast
inlet boxes rather than poured-in-place inlets under the median
barrier walls," said Brown, Good Hope's vice president-operations.
"There was one hitch. The Alabama Department of Transportation's
drawing books didn't include the inlets. So Sherman Dixie's
engineers prepared drawings, submitted them to ALDOT and got
them approved.
"Using the inlets has saved us time on that phase of
the job and put us days ahead of schedule."
Good Hope began work on the 4.3-mi. project in July and expects
to finish the job in July 2006. Federal money is financing
80 percent of the contract and state funds are underwriting
the remainder.
Already nationally certified to fabricate precast concrete
products, Sherman Dixie of Cullman began production quickly,
trucking six inlet boxes daily to the construction site. Each
9,000-lb. inlet is 3 ft. wide, more than 6 ft. long and 5
ft. deep.
"Instead of spending time erecting inlet boxes, tying
steel, pouring the concrete and waiting for it to cure several
days, Good Hope workers were able to concentrate on building
the roadbed," said Dewayne Shaddix, sales representative
for Sherman Dixie.
J. F. Horsley, Birmingham division engineer for ALDOT, said
the biggest task has been performing the work while not interfering
with traffic flow.
"We're expanding a whole stretch of I-20 from four to
six lanes in each direction," Horsley added. "Although
there are temporary tie-ups, we basically try to keep four
lanes open all the time. Between 40,000 and 45,000 vehicles
travel the road daily in the part of the interstate we're
working on. That volume increases as you get closer to Birmingham."
To keep traffic flowing, the highway department designed
the project so that traffic could be shifted 7 ft. onto the
outside shoulders. After completion of median lanes and barrier
walls, traffic will shift onto the two new inner lanes, enabling
workers to pave the outside lane.
Specially formulated Superpave asphalt is being placed over
the roadway's existing concrete pavement, which is being rubblized.
During the rubblization, subcontractor Resonant Machines Inc.
of Tulsa, Okla., is breaking the existing concrete pavement
with a guillotine breaker, which turns the concrete into road
base material for the new asphalt surface.
Good Hope first paved the outside shoulders in order to shift
traffic, then brought in fill material and paved the median
to bring it higher than the existing concrete.
"At that point, RMI is performing the rubblizing in
three stages," said Malcolm Douglas, project manager
for Good Hope. "With traffic on the outside, they're
rubbilizing a narrow 8-ft. strip on the inside so we can pave
the median and overlap the existing roadway. After we shift
traffic, they'll rubblize another strip. Then we'll do the
remaining outside lanes in the last phase."
The company will lay 1 ft. of asphalt on top of the rubblized
concrete. A multi-layered median, with a bottom layer of crushed
aggregate and numerous layers of asphalt, is 2 ft. deep.
"Pavement thickness primarily depends on soil conditions
and truck traffic," Douglas said. "While the soil
is generally good, a large number of heavy trucks travel this
road, so we need the 2-ft. buildup in the median."
A paving crew of 12, directed by Good Hope's area manager
Jim Chambers, is constructing three 12-ft. lanes on each side
of the interstate. The total width of the interstate, including
the median's barrier walls and shoulders, is 121.5 ft.
Good Hope is hauling 260,000 tons of asphalt from its nearby
Ashville plant for the project.
While paving is under way, subcontractor Alabama Bridge Builders
Inc. of Pelham, Ala., is working on three bridges. Douglas
said that work on one bridge was performed early in the project
to facilitate traffic flow.
"We had to raise the overpass bridge at Riverside exit
early in the project so we could shift traffic out onto the
shoulders," Douglas added.
"We needed to make sure vehicles wouldn't hit the girders
because the bridge girders curve a little at the shoulders.
Raising the bridge also helped us maintain the proper clearance
since the interstate is being raised."
Robert Earley, secretary-treasurer of Alabama Bridge Builders,
said lifting bridges that span interstates is business-as-usual
for his firm.
"We hook multiple jacks together in one system,"
Earley said. "A hydraulic pump supplies fluid to all
those jacks at the same time, and the jacks lift the bridge
up in increments of .5 to 2 in. As we jack up the bridge,
we put steel plates underneath.
"When we've raised it 20 in, the plates are holding
up the bridge. Then we pour concrete around the base. We just
have to be careful and not tear up what's already there."
Alabama Bridge also connected two I-20 bridges that cross
a county road and railroad tracks.
"There was a gap of about 35 ft. between the lanes of
traffic," Earley said. "We added new supports and
substructures and widened the decks over new girders so we
could add the median barrier walls."
Douglas said there are more than 22,000 lin. ft. of 54-in.-tall
concrete safety barriers that are being slip-formed the entire
length of the project to separate east- and westbound traffic.
"Alabama Slipform Inc. of Birmingham constructs the
barricades and lays out reinforcing steel to support the walls,"
he added. "It also adds empty conduits under the walls
to add lighting if it's needed later."
Useful Source:
For more information about current road construction projects
in Alabama,
click
here >>
|