|
Bridging the Gulf
Port's land area increased by 60 acres in Gulfport
By Angelle Bergeron
One man's geotechnical wonder is often mere child's play
to another. So it is with the expansion of the Mississippi
State Port Authority's port at Gulfport.
By the time W.C. Fore Trucking Inc. completes construction
of the perimeter dyke and 60-acre extension to the southwest
tip of the existing port, the Gulfport-based contractor will
have moved 2.5 million yds. of sand. WCF is using 150 to 200
trucks per day, working 7 a.m. to 5 p.m. on weekdays and a
half-day on Saturday to accomplish the feat in three years.
Although the $18.6 million contract is substantial for the
local contractor, project manager R.F. "Bob" Gavin
described the project as "a plain old dirt job; just
a lot of it. It's nothing exotic like a 50-story building
or a condo or casino. It's just moving around a bunch of dirt."
But from an engineering point of view, the soft, silty soil
conditions and compressible clays that exist on the floor
of the Gulf of Mexico presented an unprecedented obstacle.
"Thompson (Engineering Inc.) did some high-tech engineering
for this project to come up with the design to suit these
conditions," said Peter Hopkins, project manager for
URS Corp., the worldwide engineering firm that manages the
project. When the Corps of Engineers granted the MSPA approval
in 1998 for an expansion, designers assumed soil conditions
would be similar to those found when WCF did a 29-acre expansion
there in 1993.
"The previous expansion had one bad area that turned
out to be fairly common for this new 60-acre area," Hopkins
said. "When soil borings were taken and we realized what
the conditions were, we looked at many alternative methods
of construction." Engineers considered bulkheads, caissons,
sunken barges, rock and even building a conventional wharf
structure. The wharf was quickly ruled out because of the
cost.
Thompson eventually decided to use alternating layers of
geogrid fabric and sand, dotted throughout with wick drains
to help soil compression.
Two layers of geogrid were placed before any fill was added.
Next, the contractor added fill in 3-ft. lifts, allowing for
time in between while engineers monitored the subsurface soils
for sufficient consolidation levels.
"We've got three layers of geo grid and basically we
would put down the fabric, a layer of sand, wick through,
then more sand," Gavin said. "We used clean, coarse
grain sand up to a plus-two elevation (with water level being
zero), then a lesser grade once we got above the water."
The contractor began by constructing the north levee while
hauling fill for the interior acres. The constant flow of
trucks provides both accurate placement of fill and compaction,
Gavin said. The port built a separate gate entrance to accommodate
the steady stream of trucks, and WCF had to beef up its truck
fleet.
"We had some difficulty having enough trucks on a day-to-day
basis to haul all of the material and stay within the schedule,"
Gavin said.
To construct the levee, the contractor is using a barge that
holds 320-ft.-wide rolls of geo grid and a mandrill fitted
with a 4-in. feeder pipe to install the wick drain.
"We've calculated what the toe-to-toe is on the levee,"
Gavin said. "The levee is 10 ft. wide at the top and
with the slope we've got as much as 300 ft. at the bottom."
The barge gradually moves further into the Gulf, unrolling
the fabric. As trucks and dozers follow with mountains of
fill, workers on the barge join pieces of the fabric to make
a continuous levee.
A mandrill moving back and forth across the width of the
fabric strategically places the 55- to 65-ft. lengths of wick
drain.
The fabric, a uniaxial grid supplied by Atlanta-based Mirafi
Construction Materials, has been around for several years
and is commonly used in a variety of applications, said Dusty
McClure, southeast region manager.
"Uniaxial grid denotes the method of reinforcing, which
is in one direction," and the engineers chose the product
for this application, McClure said. The funny thing about
geosynthetics is that, if all goes well, no one will ever
see them, he added.
"It's good people don't see it because that means it's
working."
The wick drain is basically a plastic cord wrapped with geotextile
fabric, said Mike Obermeyer with supplier American Wick Drain
Corporation. The plastic cord produces passage for water flow
and the geotextile fabric provides a filter. Basically, it
takes the water out of the soil, consolidates it and makes
it stronger.
The use of wick drains has enormously accelerated compression
and the construction schedule.
"We went in and evaluated putting in wick drains at
different spacings to get it down to 65 to 70 days of settlement
time before putting on additional materials," said Dwayne
Smith, chief design engineer with Thompson. "Without
drains, that process would take years."
Thompson is a familiar name in the oil and gas industry and
the firm has successfully designed a number of structures
in and along the edge of the Gulf. However, this project required
some creative design and a great deal of analysis, Smith said.
"We've done several sites with soft soils, but this
one was slightly different," he added. "We have
not done a job like this where we were doing land creation
in the Gulf. We did the 30-acre expansion at the same site
in the late 80s, but the soils were twice as good as these."
To verify the design, Smith consulted with a professor at
the Massachusetts Institute of Technology in Boston.
"He mentioned that this site was one of the three worst
he has ever run across," Smith said.
In April 2003 W. C. Fore was awarded the contract for construction
of a dyke around the perimeter of a 60-acre expansion. It
filled to grade 20 acres of that area and relocated a channel
that serves a small, commercial craft harbor in the path of
the expansion.
"Part of our contract was 130,000 to 150,000 yds. that
were mechanically dredged to create that new channel,"
Gavin said. "You can't get a big hydraulic company to
come in and do that kind of job unless you've got at least
a million yds."
The project is part of a strategic master plan originally
laid out by the MSPA in 1998 and updated in 2003, which includes
a five-, 10- and 20-year vision plan, said John Webb, deputy
director of engineering.
"This is a portion of the five-year plan that will allow
us to enhance our container capabilities," Webb added.
The port handles an equal amount of imports and exports,
primarily bananas, Webb said.
Although the object of the expansion is to develop the port's
container capacity, the current project will simply create
a swatch of land that may be developed by future tenants,
he said.
"More than likely, we will use this space to allow existing
tenants to grow, or we will lease parcels to owners and allow
them to develop," Webb said.
In November the MSPA received approval from the Corps of
Engineers to increase the expansion to 84 acres as well as
add a 125-by-750-ft., pile-supported pier. Construction of
that pier and fill of the remaining 64 acres won't be open
for bid until this current project is complete.
WCF expects to finish way ahead of the 1,200 calendar-day
reference schedule.
"We will finish by the first part of 2006, maybe even
the last quarter of 2005," Gavin said.
Useful Source:
For more information about the port, go to: http://www.mscoast.org/advantages/Transportation/ports.html
|