|
New and improved
Chattanooga revitalizes Riverfront with new facilities
By Candy McCampbell
Visitors to Chattanooga's Riverfront will soon be able to
walk along - and on -the Tennessee River to a new city pier.
They'll also be able to watch river traffic from a stepped
concrete terrace built on land reclaimed from the river.
The work - which includes a new walkway that will straddle
both land and water - is being performed by Continental Construction
Co. of Memphis during a $19.9 million project to be completed
in May. The contractor will also build a new dock for the
Southern Belle riverboat, a new ramp for the Chattanooga Ducks
amphibious vehicle, a docking area for boats, a small entertainment
amphitheater for children and a passage under Riverfront Parkway
that will feature a public art display.
The project is part of Chattanooga's $120 million 21st Century
Waterfront, a public-private undertaking that includes a variety
of other expansion and renovation projects at the Tennessee
Aquarium, the Hunter Museum of American Art and the Creative
Discovery Museum.
Continental started its work in November 2003, dividing the
Riverfront project into two phases, one at the river and the
other beneath nearby Riverfront Parkway where the contractor
is building an "art passage."
At the river, the new walkway will sit on 500, 45-ft.-long,
H-shaped steel piles driven into bedrock. The piles are topped
with precast concrete slabs and a 6-in. layer of poured concrete.
"The engineers decided the river bank needed sheet piles
and rock that come up about 4 ft. above the normal pool,"
said Continental project manager Kenny Statham. "Above
that is landscaping." More than 20 tons of rock had to
be trucked in for fill along the river.
A new dock for the Southern Belle riverboat is located about
1,000 ft. downriver from its former base. Burrowing river
muskrats had riddled the old city dock's Styrofoam underbelly
with holes, and it had to be destroyed, Statham said.
Also demolished was the old city pier, which had steel pipe
piles covered in concrete below water.
"We removed the old concrete cells (where the barges
tied up) and some old concrete piers underwater," said
Gary Owens, president of Tennessee Valley Explosives, of Cleveland,
Tenn. Working from a barge, the contractor used a track drill
to bore into the caisson and insert plastic pipe in the holes,
which were later loaded with explosives.
Some of the old cells were close to the surface, so the contractor
supplemented the usual 8.5- by 12-ft. rubber blasting mats
with a 12- by 12-ft. wood frame around the cell.
The new 650-ft. city pier, stretching 200 ft. over the river,
is being built onto pipe piles as deep as 65 ft. to reach
bedrock. The river is about 30 ft. deep in that area, Statham
said.
The pier is designed with two surfaces on top.
"The top of the pier will have precast concrete along
one side and structural steel beams with bar grating on the
other," Statham added. Precast concrete panels about
30 by 5 ft. by 7.5 in. deep are placed side by side and covered
with 4.5 in. of poured concrete.
A floating dock at the end of the pier will serve commercial
and private boats, and mooring cleats along the river walk
can handle private boats. Visiting riverboats can dock at
the concrete terrace upstream.
The terraced area is "bumped out" from the original
bank, reclaiming about 6 ft. of river, Statham said.
Riverfront Parkway, about 30 ft. above the river's edge,
has been open to traffic during construction of the art passage,
except for brief halts during blasting, Statham said.
Much of the excavation for the passage had been performed
during an earlier contract, but Continental had to finish
the excavation and perform the fine grading for the small
space using tractors, a mini-excavator, a small crane on the
road overhead and "a lot of manual labor," he added.
The concrete for the work was pumped into place.
The passage is near the place where Cherokee Indians gathered
during their forced removal in the Trail of Tears. It will
have permanent Indian art designed by a team of Cherokee artists
that celebrates the tribe and its culture.
The passage is lined with walls of 16- by 24-in. masonry
cladding.
The number seven is important in Cherokee history and culture,
so walls will feature seven 6-ft. pottery medallions, seven
steel cutout figures and seven bronze "weeping"
panels with water that runs down them, then flows over tiers
of steps to a reflecting pool, all in the passageway. Pumps
will send the water back up the walls.
The reflecting pool, centered with a stainless steel sculpture
of a spider - also part of Cherokee mythology - will be lined
with 8- by 16-in., 2.25-in. thick pavers set in mortar, said
Will Saxby, project manager for ValleyCrest Landscape Development
of Norcross, Ga., the installers of the landscaping, irrigation
system and pavers.
Saxby said hexagonal 4-in. pavers are in the walkways and
a children's amphitheater built under an arch of the existing
Market Street Bridge.
The project also required that the contractor move 80,000
yds. of dirt, mostly from one end of the site to the other,
where the terrace extends over the riverbank, Statham said.
Rick Hoosier, general superintendent for East Tennessee Grading
of Chattanooga, said moving that much dirt in a relatively
narrow site - sandwiched between the river and the parkway
- involved "a lot of shuffling and a lot of cooperating"
by the contractors.
His crews also formed sharp corners at a 3 to 1 slope in
the terraced area using a small tractor followed by "a
lot of hand work," Hoosier said. "You get it as
close as you can with equipment, but have to finish it by
hand."
The sharp corners are a "signature" of Hargreaves
Associates of Cambridge, Mass., the international waterfront
design firm for the 21st Century project.
"They are renowned for the land forms and sculpted forms
they create out of dirt and grass and the surfaces they use,"
said Dan Kral, project representative for RiverCity Co., the
project development firm.
The dirt in the area - formerly industrial land - had to
be tested for public use and amended to support more than
500 trees, 3,800 shrubs and 10,000 pieces of groundcover,
Saxby said.
The riverbank is also getting 11,000 fascine bundles - live
branches of trees that grow by suckering - that will serve
as erosion control.
"In the river there will be seven water cannons with
150-hp pumps," Statham said. "The cannons will shoot
water 60 ft. to 70 ft. in the air and 100 ft. out."
Because it is part of the Tennessee Valley Authority system,
the river remains at a fairly consistent level, varying only
a few feet with power generation outflow at Chickamauga Dam
upstream, Statham said.
|