|
Back to the past
Entergy 'lifeboat' protected as Jackson building restored
By Angelle Bergeron
The tallest crane in downtown Jackson is perched directly
beneath an old Mississippi Power & Light logo that graces
the front of the Electric Building on Pearl Street.
The 200-ton crawler crane, which is positioned to stay clear
of nearby traffic, is being used in a $12.6 million restoration
project that will bring Jackson's Electric Building back to
its 1927 glory.
It's the latest project by Harrell Contracting Group of Ridgeland,
Miss.
In late December the crane's 145 ft. of boom began erecting
steel on the rear side of the building, which was originally
called the Lampton Building and has spent most of its life
as home to the power providers of the Southeast.
When Entergy decided to reconsolidate its local offices,
the old building seemed too much of a challenge for the power
company.
"They had made the decision they didn't want to renovate,
so they put the building on the market," said Ted Duckworth,
owner of Jackson-based Duckworth Realty. "It looked like
an interesting project and we didn't want to see the building
go dark."
Even though Duckworth had never embarked on a historic restoration
project, he had several new acquisitions in the downtown area
and thought the tax incentives for historic structures were
too good to pass up.
"We simultaneously acquired the property and started
construction last September," Duckworth said.
When complete, the 10-story building will house retail space
on the first floor, two floors of office space, all of Entergy's
offices (floors four through eight) and luxury apartments
on the top two levels.
"It was very complicated assembling the deal, but finding
the right tenant mix for the retail space will be the biggest
challenge," Duckworth said.
Finding the right contractor was easier.
"Harrell had worked hard on two similar historic renovations
in the downtown area, so I knew they could do the project,"
Duckworth added.
Harrell, which does about $80 million annually, is heavily
involved in renovation/restorations all over the Southeast.
In August Harrell began value-engineering work with Duckworth
and architect Johnson, Bailey, Henderson, McNeel of Jackson.
The contractor began the demolition after the owner acquired
the property.
Harrell's contract includes complete demolition of the interior
space, exterior restoration and construction of a new core.
The project should be completed by the third quarter of 2005,
said Tom Black, Harrell vice president.
The original poured-in-place concrete structure, which is
still structurally sound, had undergone two renovations in
its history. In 1966, a steel structure was added on the east
wing and in the 1950s the "U" of the building was
filled in from floors one through four and the structure was
"modernized" by covering parts of the exterior and
first floor interior with granite.
"The materials were nice, but they weren't historic,"
said architect Richard McNeel. "Also, nothing met code.
We had to create a new core for the building with restrooms
and fire stairs."
Removing the granite was a unique challenge, said Brian Corley,
project engineer for Harrell.
"The whole first floor - columns, walls and floors -
was covered in 2-in.-thick granite," he said. "Some
of the pieces were 4-by-6-ft. and about 750 lbs."
Harrell will be infilling the remaining U-portion of the
building to add the necessary core and transform it into a
rectangle.
"The existing roof level over the 1950s infill area
(on the fifth floor) comes off, and that's where our new structural
steel goes," Corley said.
In November, Harrell began the tedious job of excavating
the existing columns in the U-area so the concrete footings
and columns could be enlarged to support the additional load.
The 3- by 3-ft. footings were enlarged to 8 by 8 ft. and the
14- by 14-in. columns were expanded to 26 by 26 in. using
epoxy, new rebar and concrete.
Erecting the structural steel will require a lot of finesse.
"The back side of this building is about 10 ft. from
St. Andrew's Cathedral and the governor's mansion is across
the street from there," Corley said. "We're going
to operate the crane by radio and erect the steel from the
crane in the front of the building. The operator can't see
a thing when he's doing it."
Jackson-based Bracken Construction will perform the steel
erection.
During the demolition and construction, Harrell has strict
orders to ensure the safety of Entergy's main communications
hub on the seventh floor.
"It's called the 'lifeboat,'" Black said. That's
the nickname given the entire communication network for the
southeast region, and Harrell has been repeatedly reminded
of its significance.
"We can't shut it down," Corley said. "It
would cost about $1,000 per millisecond of lost time."
The hub occupies about 20 percent of the seventh floor and
is fed by a protected chase of pipes and wires that runs from
the basement, Black said. Harrell has waterproofed the area
and introduced 400 cu. ft. per minute of positive air pressure
to keep out dust.
Demolition and the core addition were complete by the end
of December and Harrell begins working on interior and exterior
finishes this month.
To receive tax credits the owner had to restore several exterior
components from the building's original period and ensure
modern conveniences on the interior.
"We were downtown with limited site space, taking a
1920s building and upgrading it without removing that historic
flavor," McNeel said.
Using original construction drawings, old post cards and
photographs, the architect was able to piece together certain
elements that needed to be addressed.
"The building had been reglazed without a historic window
design and it looked bad," McNeel said. Jackson-based
Creative Windows is installing a period replica.
Much of the original terra cotta decorative work on the first
three floors had been shaved off and what remained was in
dire need of refurbishing. Fort Worth-based Casting Designs
Inc. is manufacturing copings, urns, door surrounds and rope
moldings of glass fiber reinforced concrete that look like
terra cotta.
Western Waterproofing Co. of America of Grand Prairie, Texas,
is installing the new finishes and refurbishing the existing
terra cotta. The subcontractor will do various other masonry
restorations on the building.
On the interior, the 10-ft. floor-to-floor space made it
difficult to include the latest telecommunications and cooling
systems.
"Modern buildings are closer to 13, 14, even 15 ft.,"
McNeel said. "That dimension gives you room for ductwork
and all kinds of stuff this building didn't have. It was a
fun challenge."
The architect suggested a perimeter fan coil unit system,
which eliminated the need for ductwork. Telecommunications
and data are housed in the 2.5-in. raised floor that was created
in all of the office areas.
"Floors nine and 10 have 15-in. raised floors to facilitate
plumbing in those areas (for apartments)," McNeel said.
|