|
Warming the mix
Contractor heats Little Rock high-rise slabs during winter
construction
By Mark Friedman
Moses Tucker Real Estate Inc. of Little Rock recently unveiled
a new mixed-use commercial building in the city's downtown,
its second in the last two years.
The $26 million First Security Center, a 12-story, 168,000-sq.-ft.
tower, sits on a quarter block in the heart of Little Rock's
River Market.
"We think there was a demand for the product,"
said Jimmy Moses, a partner in Moses Tucker, which also opened
the seven-story, $11.5 million Arkansas Capital Commerce Center
in 2002 in the River Market.
First Security Center will feature a Marriott hotel on floors
one through six, office space for the brokerage firm Crews
& Associates of Little Rock on floors seven through 10
and 24 luxury condominium units on the top two floors.
CDI Contractors LLC of Little Rock began work in June 2003
by demolishing a vacant masonry building at the site.
The general contractor's plan for constructing the building
was to "treat it like three different buildings, even
though they're all stacked on each other," said John
Moore, CDI's project administrator.
Each section was "totally different," Moore added.
"And none of the plans for either the hotel or the condos
were buildings that had been done before, so this was all
a totally customized unit. There's no question this is the
most difficult project I've been on."
"The blending of the hotel, office space and condos
was a real challenge," said the project's architect,
Tom Adams, president of Wittenberg Delony & Davidson of
Little Rock. Each of the three building types has its own
requirements and requests.
All the mechanical systems had to line up and work together
throughout the building, "so it required an unusual amount
of mechanical, plumbing and electrical coordination, more
so than in most (buildings)," Moore said.
The floor-to-ceiling heights also varied. In the hotel, the
ceiling height is 8 ft. 6 in., while it rises to 10 ft. on
the condo floors and 14 ft. 6 in. on the office floors.
Adams had to respond to a variety of tenant requests when
designing the building.
The condo owners "wanted to have floor-to-ceiling glass
as much as possible," he added. "The hotel was the
opposite. It didn't want to have that much glass. And the
office space sort of fell in the middle."
Everyone seemed pleased with the design, though. During the
construction, all 24 condominium units were sold.
From the beginning, CDI was on a tight schedule because Marriott
needed to be opened for the ribbon cutting of the William
J. Clinton Presidential Library in November.
That meant the tower had to be built during the winter, Moore
said.
With the tower slabs being made of post-tensioned concrete,
CDI had to cast each floor in place on a temporary plywood
table customized for the project.
Typically a project like this would have been built in the
summer.
"You can't pour concrete when it gets below 40 degrees,
so you have to use cold weather techniques," Moore added.
CDI draped industrial tarps on the sides of the structure
and turned on gas heaters underneath the floor where it would
be pouring the 5,500-psi concrete.
That's done so the water-based concrete won't freeze, Moore
said. "That's why you literally heat (the floor) like
a stove," he added. If the slab froze, CDI would have
to remove the concrete and start over.
"We had some delays due to freezing conditions (but
the slab didn't freeze)," Moore said. "We had to
work hard to avoid it."
The contractor also had to make sure the concrete delivery
trucks snaking their way through downtown Little Rock didn't
get tied up in traffic.
"Those concrete trucks can't be interrupted, because
you can't have a slab partially cure," Moore said. To
avoid traffic problems, CDI began pouring the slabs around
midnight and concluded about 10 a.m.
CDI had to coordinate with the local gas, electric and phone
companies to determine where underground pipes and cables
were, Moore said.
"In some cases the utility companies didn't even know
what was underneath the ground, and we would dig and find
something we didn't know was there," he added.
He said CDI uncovered railroad tracks that weren't on any
of the maps and workers often hit "huge, round smooth
boulders" when drilling through the sandy riverbank soil
during foundation construction.
Adams said he chose brick for the building's exterior to
give it "a warehouse feel." But trying to place
bricks 14 floors off the ground caused problems.
Moore said a Bennu scaffolding system was used to get the
job done. The platform scaffold sits on the ground and enables
workers to add two-story vertical sections as they work their
way up the building.
"It's like the steel frame scaffolding that you see
on a lot of high-rise buildings," Moore said. "There
would be no way to build the building without (the Bennu system)."
Because of the success of the first two projects, Moses Tucker
announced at the end of October that it would build another
tower in the River Market, which will be a 17-story, $45 million
residential building.
"We believe based on our previous success that there
is a demand for high-end luxury condominiums," Moses
said. "And there's no better place to put them than on
the top floors of a building."
Useful Source
For information on other current and future projects in downtown
Little Rock, go to: http://www.downtownlr.com/attractions/
|