|
Value engineering
Knoxville interstate clears formidable design hurdle
By Candy McCampbell
When two proposed retaining walls flanking a bridge over
Interstate 40 in Knoxville were estimated at about $1,300
per sq. ft. - more than 10 times the usual cost - engineers
decided to take another route.
As proposed, the $30 million concrete walls would add another
30 percent to the $62.4 million road-widening and improvement
job. The retaining walls are going up near the North Winston
Road overpass at one end of the project.
Saieb Haddad, geotechnical engineer in the Tennessee Department
of Transportation's Knoxville office, worked with Henry Pate,
engineer at TDOT's Nashville office, to find another option.
They came up with a pile-framed retaining wall that could
be built in minimal space within the existing right-of-way,
eliminating the need to spend $15 million to $18 million purchasing
an office building and large retail store nearby, Haddad said.
The cost of the revised plan: an estimated $75 per sq. ft.
"People come up with different types of walls, using
different types of technology," Haddad said. The new
wall uses a battered pile form with coping on top of it. The
battered face is at a 70-degree angle.
"The longer the battered face, the longer the base will
be. The more the better" because it makes the wall stronger,
he said.
The area's geology - clay over irregular limestone bedrock
- requires varied depths for the wall piles, some reaching
more than 100 ft. Reinforcing steel encased in cement provides
additional stability.
Studs were welded to the beams to hang rebar and hold temporary
wood lagging. The surface was covered with a molded stone-like
concrete finish.
The piling framed retaining wall can be used "in any
similar situation," Haddad said, and is being considered
for a major interstate project in downtown Knoxville to be
let in 2005. In fact, the design has won a TDOT award and
a cost-savings award from the Tennessee General Assembly's
Fiscal Review Committee.
Even with the wall design changes, it was the biggest interstate
highway job in the state when it was let in late 2002. Two
others let since then, both on I-40 in Nashville, are bigger.
The 4-mi. Knoxville job, which starts at Papermill Road,
includes 12 bridges, 16 ramps, the complete reconstruction
of the Papermill Road and West Hills interchanges and the
addition of a partial interchange at Weisgarber Road, said
Chad Woodroof, project manager with Charles Blalock &
Sons of Sevierville, Tenn., the general contractor.
A collector road is also being built on the north side of
I-40 between Papermill and Weisgarber and a frontage road
is to be constructed on the south side near the West Hills
interchange.
It's in a high-traffic area, where both I-40 and I-75 share
the same roadbed. More than 152,000 vehicles travel that stretch
every day, making it the seventh busiest in the state, according
to TDOT.
Woodroof said the project is eligible for early completion
incentives of $7,500 a day, so "we jumped in with both
feet with an unbelievable amount of resources and equipment,
moving dirt and starting on walls and roads."
Planning helped minimize weather-related slowdowns in late
2003 and early 2004 so that concrete, retaining wall and utility
work could continue uninterrupted. But in May, rain delays
held monthly payroll to almost half its usual $1.4 million,
Woodroof said.
Bridge builder McKinnon Construction Inc. of Knoxville was
able to work during most of the winter when "the dirt
operation shut down," said owner Mark McKinnon.
About 150 workers are presently moving 1.3 million cu. yds.
of dirt, re-using 300,000 tons onsite and hauling off the
rest. About 100,000 cu. yds. of rock are also being removed.
"The new road will have a base of 10 in. of stone, topped
by five lifts of asphalt totaling 14.75 in. thick," Woodroof
said.
Two in. of asphalt will be milled off the existing roadbed
and another 2 in. added by Renfro Construction Co. of Knoxville.
The milled asphalt is taken to Blalock's plant and recycled
for later use.
More than 260,000 tons of base stone and 177,732 tons of
asphalt will be placed during the project. Also needed are
about 2.8 million lbs. of reinforcing steel, 18,000 ft. of
pilings, almost 3,300 ft .of pre-stressed concrete beams and
2,700 ft. of pre-stressed concrete box beams.
McKinnon said the bridges are taking up 250 tons of steel
and about 4,500 cu. yds. of poured-in-place concrete.
"Under it all is more than 5 mi. of concrete pipe -
ranging from 18-in. to 54-in. diameters," Woodroof said.
He added that coordinating the utility work has been tough
because much of the underground lines have been a "huge
puzzle."
Brent Wilson, vice president of Pipeline Construction Inc.
of Rogersville, Tenn., said his company is laying gas, water,
sewer lines and underground electrical conduit, and has bored
under I-40 in six locations.
The pipeline work also runs along heavily traveled Kingston
Pike at the West Hills interchange.
David McDuffie, operations vice president at Pike Electric,
said this is the first TDOT project where the general contractor
included the utility work in his bid.
"This has given the contractor more control and improved
communication at the jobsite," McDuffie added. "It
has really worked well."
Useful Source:
For more info about east Tennessee projects, go to: http://www.tdot.state.tn.us/projects/east.htm
|