|
Blasting a trail
Contractor builds through solid rock to four-lane MS Highway
6
By C. Richard Cotton
The ocean that covered north Mississippi eons ago left behind
surprises still being discovered today. Even sharks' teeth
are found in sand formations around the region.
Sometimes, long-buried surprises pop up in the most unexpected
places - like near the western terminus of the MS Highway
6 construction in Pontotoc County.
"We had to remove 170,000 cu. yds. of solid rock,"
said John Robbins, project manager for Eutaw Construction
of Aberdeen, Miss., the prime contractor for the $32 million
project that will four-lane 7.2 mi. of the highway.
Robbins learned from Mississippi Department of Transportation
officials that the rock was once a coral reef. "It was
a solid strata of rock that was a change to the project,"
he added. Rocks of that magnitude are unusual in the area
around Pontotoc County, which lies directly west of Tupelo.
More common are streambeds strewn with gravel.
Nonetheless, the ancient reef had to be dealt with. Eutaw
crews set about the task with hoe rams, busting the large
rock into smaller more manageable pieces. That excess was
disposed of as unsuitable for fill on any part of the project,
Robbins said.
Part of the state's continuing four-lane program that was
initially launched in 1987, MS Hwy. 6 will eventually bypass
Pontotoc. The current route is a two-lane bottleneck that
includes a confusing turn, traffic signals and stop signs.
The new highway hooks up north of Pontotoc with four-lane
MS Highway 76, which was built from Oxford to MS Highway 9
several years ago; MS 76 will be rededicated as MS 6 upon
construction of the current segment.
When the construction phase is completed to MS Highway 342,
about 11 mi. of two-lane MS 6 will remain between the new
highway's eastern terminus and Tupelo. Long-range plans call
for MS 6 to eventually loop around Tupelo.
Besides the solid coral-reef rock, another 755,000 cu. yds.
of excess dirt was also hauled away, while 550,000 cu. yds.
were used for fill. The total excavation for the project topped
1.4 million cu. yds.
"That is the biggest task," Robbins said.
The western two-thirds of the project is new alignment, while
the eastern third is new lanes that parallel the existing
highway, which will become a frontage road for the new thoroughfare.
The Longview Road overpass and a fly-over bridge to connect
the old MS 6 sections together and to provide an entrance
ramp to the new sections have yet to be constructed. Their
construction will complete the contract of N. L. Carson Construction
Co. Inc. with Eutaw.
"We have built four bridges already," said Lee
Carson, vice president of the firm founded by and named for
his father in 1973 and based in Carthage, Miss.
The six bridges are all pre-stress concrete beams topped
with precast concrete panels; the first constructed was the
MS 9 overpass at the western terminus of the new project.
Carson said that bridge and one other required 36-in.-diameter
drill shafts - nine per bridge - rather than the standard
pilings that were driven for the other bridges.
"The soil was not conducive to pilings," he said
of the shafts drilled 30 to 40 ft. deep. The firm has experience
in both hard and soft applications, much of it from extensive
work in Alabama, Carson added.
Carson expects his crews to return to work on the project
about April 1. He predicts completion of the remaining two
bridges by October.
Eutaw crews have let the project lay since winter set in.
The only active work crews have been from APAC of Mississippi,
which is placing asphalt pavement as weather allows.
Keith Kelly, APAC construction manager, said his firm is
about 15 percent complete with their share of the project.
The company is expected to place more than 300,000 tons on
the project, comprising four different asphalt grades in five
separate lifts.
Lee Hall, owner of Hall's Construction Co. Inc. of New Albany,
Miss., said his work is about three-quarters complete on the
highway's box culverts.
"We have two to finish and two to build," Hall
said.
The largest of the six he contracted to build was a 12-ft.
by 16-ft. double-barrel structure more than 500 ft. long.
It took his crews three months to pour more than 1,500 cu.
yds. of concrete in the culvert's five sections. Each section
required three different pours and, with the headwalls and
aprons, totaled 20 pours.
Hall said he expected to be back on the job in early spring,
too, with completion of the two partially built boxes coming
in four to six weeks after that. The remaining two boxes are
in the transition area of the old and new highway. They will
be built, possibly next fall, when traffic is moved off the
old highway onto the new highway.
Robbins said the project was 47 percent complete as of January;
only 26 percent of the allotted contract time had been used.
Although the contract completion date is September 2006, Robbins
planned to turn it over to the state in mid 2005.
Eutaw is named after the rock strata common in the area.
Owner Tom Elmore founded the company in 1980.
|