|
Streamlining traffic
Nashville diamond interchange requires work on 10 bridges
By Mardy Fones
Construction of a new diamond interchange on the footprint
of one built in the 1960s is at the heart of a $43.6 million
highway project in Nashville.
The 36-month, Interstate 40/Robertson Road project includes
expanding I-40 from three to five lanes, widening bridges
and constructing new ones.
For Ray Bell Construction Co. Inc. of Brentwood, Tenn., the
final result will be separating local traffic from through
traffic without substantially altering the residential areas
and small business districts that abut the interstate.
A requirement of the project is that the existing three traffic
lanes of I-40 and nearby Briley Parkway interchange remain
open, since they carry 103,000 cars and 36,000 cars on a daily
basis.
"Ray Bell has a reputation for taking on the toughest
jobs in the industry," said Bruce Nicely, vice president
of the bridge division.
Ray Bell was founded in 1970 and bridges are its specialty.
That's a good thing because the I-40/Robertson Road project
has 10 - six that are being widened and four new ones, including
two fly-overs. One bridge is just a few feet short of a mile
long.
Other Ray Bell bridge projects have included a $52 million
rebuild of the I-240/I-40 Memphis interchange and the $29
million, 540-ft. clear-span bridge across the Cumberland River
in Nashville.
At completion, the I-40/Robertson Road project is expected
to streamline traffic flow to and from the north.
"Overall, it will be a better, more functional interchange
because it eliminates double red lights and traffic tie-ups,"
said Jeremy Mitchell, project manager.
Traffic control planning is a big part of the job and has
been ongoing and collaborative, said Larry Ridlen, the principal
in transportation services for Gresham Smith Architects and
engineer of record on the job.
"With Ray Bell's help, we tweak the plan every week,"
he added. "The difficult part is finding space (along
the interstate) to work."
To date, there have been no lost-time accidents.
"It's gotten real dangerous to do road projects, said
Dennis Howell, project superintendent. "It takes people
with bridge experience and nerves to work 75 ft. up in the
air."
Howell added that another difficulty was setting the 70-plus
piers that support the bridges. The piers are located inches
from speeding traffic. Most are set on caissons, others are
on spread footings. All required some blasting or extensive
excavation, in one case to a depth of 60 ft.
Another caisson was set within a few feet of the back of
a building because a ramp of one of the bridges extends 12
ft. over it.
Protecting Rock Creek, which runs parallel with I-40 from
run off, was another priority and required the construction
of new box culverts and redirecting the streambed.
Purchasing rights-of-way in the densely populated area took
time and was expensive. Acquisitions began in early 2000 and
were completed in summer 2002 at a cost of $10.3 million.
Mark Halloran, director of Region 3 for the Tennessee Department
of Transportation, said only nine of the 151 tracts required
litigation; 68 resident relocations and two business relocations
also occurred.
The state also purchased air rights over a strip mall and
bowling alley to construct one of the fly-overs.
The installation of new utility service under I-40 required
Mitchell Plumbing of Nashville to hand dig a 400-ft., 54-in.-diameter
tunnel. Blasting to carve through solid limestone took teams
of three diggers four to five months to complete. The project
also includes 20 reinforced retaining walls, 16 of which were
cast in place, plus a 1,700-ft. noise abatement wall.
By February, Bell personnel were lifting into place the 313,
150-ft.-long concrete beams manufactured by Concrete Products
of Memphis. That piece of the job was reserved for weekends
when traffic could be cut to one lane so 300-ton cranes can
be moved onto the interstate to lift beams individually into
place.
Each beam is manufactured of rebar, post-tension cable and
140,000 lbs. of concrete. The beams, laid five to eight across,
span the piers.
"The beams are designed to carry the load and everything
is cantilevered off them once the concrete is poured in place,"
Howell said.
Halloran said the pre-stressed concrete beams, 80 percent
of which are bulb-tee type, will total almost 10 mi.
As spans between the piers are secured, crews follow by installing
the metal decking and rebar, then pumping concrete into place.
Overall, the job includes 2.1 million pounds of reinforcing
steel and 8,968 cu. yds. of concrete. In total, the project
has 10,550 ft. of bridge length.
The project is on track to meet its completion deadline of
Nov. 1, 2005. An incentive built into the job pays Ray Bell
an additional $7,500 for each day the project is ready ahead
of schedule, with a cap of $2.5 million. If it misses the
deadline, Ray Bell pays the state $7,500 daily with no cap.
Mitchell said it's too early to predict early completion.
The second phase of the project may be let in 2006. The project
was divided in half to minimize traffic and community disruption
as well as to keep costs down, Ridlen said. Splitting the
job also increases the numbers of contractors available to
bid on it.
Ridlen said two additional flyovers will be created during
phase two to accommodate traffic onto Briley Parkway from
the south.
|