|
Moving ahead
Third 'Stack' phase becomes one of largest MDOT projects
in history
By Angelle Bergeron
Kenneth Collins recalled working on designs for the four
phases of "The Stack" in Jackson, Miss., when he
first joined Michael Baker Engineering some 20 years ago,
a telling commentary on the longevity of the Mississippi Department
of Transportation project.
"Baker designed all four parts of the original Stack
contract," Collins, a project manager with the company's
Jackson office, said. "It was the second or third job
after I joined Baker."
After waiting all these years for his designs to be implemented,
he is excited to finally see the fruit of his labors.
"You design a lot of bridges and a lot of times you
never see them," he said. "For this to be going
on in our back yard is pretty unique and I think it will help
a lot."
The Stack, so called because it is the only multi-level Interstate/highway
interchange in the state of Mississippi, was designed to alleviate
the traffic flow within the confluence of Interstates 20 and
55 and U.S. Hwy 49. Following construction of the interstate
system through the Jackson area, traffic (specifically on
the east/west I-20) increased dramatically with the growth
of the city and daily commuters.
Likewise, truck transports traveling north and south through
Jackson on either US 49 or I-55 increased, creating bottlenecks
on the stretch of I-20 between the two.
The $58 million Stack Phase III, now under construction,
represents one of the single largest projects ever tackled
by MDOT.
"Not only is it one of our biggest projects because
of its size, but also because it is in a large metro area
with a large amount of daily traffic," said Amy Frederic,
special projects officer with MDOT's external affairs division.
The contract for The Stack Phase I was let in 1992 and Phase
II followed in February 1997. Phase I included construction
of a section of southbound I-55 from the Pearl/Pascagoula
Street exit to I-20, said Frederic. Phase II involved the
widening of the northbound I-55 bridges over US 80 in Pearl
River and overlaying of pavement from I-20 to the Pearl/Pascagoula
interchange.
The Stack Phase III was awarded to Hill Brothers Construction
& Engineering Co. Inc. in November 2002 and the company
began work in March of this year.
"The contract is among the largest single contracts
ever awarded to Hill Brothers," said Paul Leonard, project
manager. "Although we have completed projects on I-55
and various other projects throughout the state, this is the
biggest."
The project includes the reconstruction of more than five
miles of I-20, I-55 and US Highway 49 and construction of
a new fly-over bridge connecting the three roadways.
"The ultimate goal is the elimination of a lot of weaving
of traffic from 49 northbound and I-20 westbound to I-55 northbound
and I-20 westbound," said Collins, whose firm won the
CE&I (construction, engineering and inspection) contract
and is overseeing daily construction for MDOT.
Currently, traffic traveling northbound on US 49 desiring
to continue north on I-55 must make a loop to I-20 westbound
and then weave across two lanes to connect to I-55, Collins
explained. Likewise, those traveling I-20 westbound and desiring
to take I-55 northbound must weave across one lane to take
the I-55 exit.
"It's fairly unique because U.S. 49 is flying over interstates
and ramps and coming back to the other interstates,"
said Freddie Stokes, assistant district construction engineer
of operations for MDOT. "People will no longer have to
jockey for position to switch lanes."
Stokes, who oversees project field offices for MDOT in central
Mississippi, said he is treating Michael Baker as another
field office that is handling all the day-to-day operations.
"Things are flowing real well on the project,"
said Stokes. "The contractor is doing an excellent job.
He's on top of everything. It's been rather pleasant for a
project of this size to go as smoothly as it has."
Hill Brothers' contract includes the construction of seven
bridges, an asphalt and concrete roadway, and drainage that
consists of box culverts, pipe, box-bridges and inlets.
The majority of the work, which was designed outside of existing
traffic to reduce impact, is being done during the day, Stokes
said.
"When we actually do the part over the interstate, we
will have to do rolling lane closures for setting beams, etc.
and will probably do that at night," he added. "That
will only be a short duration compared to the entire life
of the project and won't be until the end of 2004 or later,"
he added.
Still, a buffer zone was created between the traveling public
and the work area, using concrete median barriers. Provisions
for traffic control and service patrol are included in the
Hill Brothers contract.
"Hill Brothers has implemented the Baker/MDOT pre-determined
traffic control plan," Leonard said. "However, coordination
of the plan with the construction methods is the greatest
challenge we've encountered to date on this project. As the
traffic control plan designates our work areas, Hill Brothers
broadcasts a construction work schedule via a Web address
to modify and alert the public of future and current lane
closures."
In addition to lighted signs (on the boundaries of each edge
of the project) that alert motorists of upcoming construction
and speed limits, Hill Brothers has implemented a service
patrol for the duration of the project. A tow truck monitors
the construction area round the clock and is available, at
no expense to motorists, for any problems. The free service
also provides tows of abandoned vehicles to a designated place
in an effort to keep medians safe.
"The service patrol has been very helpful, and MDOT
has received many compliments and positive feedback,"
said Frederic.
Because the plans were old, Michael Baker Engineering did
some updating before construction began on Stack I and II.
The same was required on this third phase, and Collins participated
in the design changes.
"Originally, the interstate pavement was not to be replaced,
but since so much time has passed it was decided the pavement
(on portions of I-55 only) was so bad that it did need to
be replaced. That affected the traffic control plan,"
Frederic said.
Actually, the original designs, rather innovative at the
time, are still considered quite an effective solution.
"There are about six bridges involved, all complicated
geometrics with a basket weave of two ramps requiring a straddle
bent design that's somewhat complicated," Collins said.
"Where the two roads cross at an acute angle, and one
that spans another, you have to have a bent that straddles
the road beneath."
The steel-span design, however, reflects a simplistic solution
to maintaining traffic on I-20 when placing the girders.
"If it was something requiring forming, it would take
longer," Collins said. "This also reduces the amount
of down time on the interstate. All lane closings are at night
and on weekends and our goal was to maintain all lanes of
traffic while construction is going on."
A special 12-hour set concrete was needed in a few portions
of the project in an effort to impact traffic flow as little
as possible. Whereas the original designs called for four
lanes of traffic on I-55 northbound, "we squeezed in
five lanes and reconfigured the number of lanes merging from
49/I-20 traffic," Collins said.
For the seven steel span and concrete girder span bridges
included in the project, Hill Brothers used approximately
19,000 cu. yds. of structural concrete, along with 91,000
lin. ft. of concrete piling, said Leonard.
"The project also included 800,000 plus cu. yds. of
borrow excavation, 90,000 sq. yds. of concrete pavement, 150,000
plus tons of asphalt pavement and approximately 2 mi. of drainage
structure," he added. "In addition, subcontractor
Superior Asphalt has designed a low-rut, 9.5-mm polymer modified
surface mix specifically for the Highway 49 and frontage road
sections of the project, which are areas that receive large
amounts of heavy traffic."
The Stack Phase III is scheduled for completion in December
2006 and Hill Brothers is on schedule.
"I think Hill Brothers is doing a great job," said
Collins. "We've got a great relationship with MDOT and
it has been a success all the way around."
So far, it hasn't even been determined whether Michael Baker
will update the Phase IV plans or not. However, the contract
for construction on Phase IV is scheduled for bid October
2007.
|