|
Linking Memphis
East-west trolley line offers new downtown route
By David Yawn
Falkner, Miss.-based Hill Bros. is wrapping up a major trolley
line expansion in Memphis, and for the first time in about
50 years passengers will be riding the rails on east-west
transits.
The $24 million Memphis Areas Transit Authority project will
offer a new route on the downtown rail route, which until
now included the parallel Main Street and Riverfront portions
running north-south across the traditional central business
district.
|
"By extending to the Medical Center, we are connecting
the second largest concentration of activity in the region,"
said Tom Fox, assistant general manager for planning and capital
projects at MATA. "We're providing access to a number
of hospitals, but also to the University of Tennessee Health
Science Center, Southwest Tennessee Community College, Southern
College of Optometry, LeBonheur Children's Hospital and other
points."
Hill Bros. began construction in December 2001 and reached
the 80 percent to 85 percent completion milestone last summer.
The project should be completed this month.
The 2-mi. route extension runs east and west down Madison
Avenue, with a terminus at Cleveland Avenue. The track itself
goes almost to Watkins Avenue, which serves as a turnaround
point.
Daily ridership on the existing legs of the trolley system
averages 2,600, with more on the weekends, especially during
events, Fox said. The summer is typically higher than the
winter.
"We think the Medical Center line will be less prone
to (ridership numbers) variations," Fox added. "There
will be a lot of mid-day trip making within the line itself,
possibly between LeBonheur and Methodist or UT to and from
downtown. The places in Memphis where parking is most restricted
is downtown and the Medical Center district, so it saves people
time and money for moving cars on short trips."
Vintage and refurbished electrical trolleys are being used,
though the rail and supporting bed are being built to specifications
that will accommodate light-rail vehicles in the future, Hill
Bros. project supervisors said.
The work includes tracks, two power substations, signal switching
room, some retaining walls and seven trolley station structures
in six locations. That's in addition to renovations on an
existing station at Main and Madison. The primary construction
work also involves overhead electrical systems. The overall
work calls for more than 5 mi. of concrete-embedded railroad
track, along with a half-mile of ballast track and 800 ft.
of bridge track, said Danny McAlister, marketing manager for
Hill Bros.
MATA and Hill Bros. agree that working in a dense urban environment
was difficult in terms of maintaining traffic flow and access
to businesses along the route.
Also, records of the old infrastructure and the street were
not always accurate, so there were a few underground utility
routing surprises.
Coordinating with utilities was important because companies
such as Memphis Light Gas & Water Division and telecommunications
firms have utilities and fiber optic lines under Madison.
Each was contracted individually to move their lines, Fox
said.
"Day-to-day coordination of the project with 14 sections
is very complex, with each section having as many as six phases
of operation - and with (at least half that number) of the
sections under construction concurrently," McAlister
said. The project had thousands of linear feet of saw cutting,
roadway removal, structural excavation, storm drainage work,
curb and gutter removal and replacement, installation of traction
power, track signalization, sub-base preparation and more,
he added.
It also required 15,000 cu. yds. of concrete work, overhead
and underground contact systems, rail welding, installation
of track and bases.
A chief logistical task was the interlocking intersection
of the existing line at Main and Madison into the new east-west
line. An underground basement was reinforced and new signalization
introduced - all against the backdrop of a programmed and
timed shutdown of the north-south running trolley line.
Bob Joyal, special projects manager and Jeremy Carpenter,
project engineer, said they are particularly proud of the
safety record: more than 620 days without a lost-time accident.
Joyal said at least one traffic lane was kept running in each
direction for the duration of the project. The major portion
of the continuous track is laid in a 14-in. concrete-reinforced
bed, he added.
The rail is cast in place and embedded in a rubber boot, or
in other needed instances, with elastomeric grout. On the
approaches to the Danny Thomas Boulevard Bridge, the rail
was placed with concrete ties and ballast.
An elaborate, multi-pole overhead system that supports the
contract wires and related hanging assembly was yet another
element of the involved project. More than 200 of these poles
had to be aligned and anchored into the ground.
Delon Hampton & Associates' project team oversaw the design
work on the MATA trolley extension project from its Atlanta
office, sending professionals to Memphis on a regular basis.
"It brings together various nontraditional civil engineering-type
work in that it has the rail aspects and traction power, signaling
and overhead contact system elements," said George Obaranec,
project manager with Delon Hampton & Associates. For instance,
the breadth and specialization of these elements brought to
bear the need to coordinate carefully to ensure compatibility
for each element of construction.
The requirement to work in a busy urban environment posed
special challenges in that the work had to carry on while
permitting traffic flow and as normal commercial activity
in the affected areas as possible, he said.
"This involved coordination with other bridge construction
going, new school construction downtown as well some apartments
being built in that vicinity," Obarenec added.
The overall benefit will be an improvement to the downtown
and medical center areas with the extension of this trolley
loop system.
Hill Bros. was formed in 1978. The company grew from a heavy
earthwork contractor to a diversified heavy highway, road,
rail and bridge contractor.
Over the years, it has been involved in the four-laning of
Highway 61 from the Tennessee line to Tunica, the Winchester
Tunnel Project at Memphis International Airport, and the Corridor
X Highway 78 Bypass project around Jasper, Ala. The company
employs more than 600.
"We have been recognized for our highway, road and bridge
construction, however, our diverse work history also includes
industrial and commercial buildings, landfills, railroad projects,
sewer, draining and power plants," McAlister said.
Prime engineer on the MATA project was Delon Hampton &
Associates. Project consultants were: Parsons Transportation
Group (electrical); E.W. Moon Inc. (sewer and storm drain);
Self Tucker Architects (architect); Jamnu H. Tahiliani &
Associates (structural); Birmingham Engineering & Construction
(soil and geotech); S.A.Williams, Inc. (cost consultant);
and Ritchie Smith Associates (landscape). |