Expanding Village Creek
Treatment plant upgrade provides more protection for residents
By Deborah Lockridge
A massive wastewater treatment plant upgrade near Birmingham,
Ala., will help keep residents living along a flood-prone
urban creek from being exposed to raw sewage and pollutants.
Alabama's Jefferson County is in the midst of a major expansion
of the Village Creek Wastewater Treatment Plant, the second
largest of nine plants in the county. The $71.87 million project
is scheduled for completion in June.
The project is the result of a settlement of a federal lawsuit
alleging violation of the Clean Water Act. The county admitted
dumping untreated or partially treated sewage into creeks
that feed the Warrior River, including Village and Valley
creeks, as well as into the Cahaba River.
In a 1995 settlement, the county agreed to upgrade the sewer
systems, with a major part of the money going to upgrade the
Valley and Village Creek wastewater treatment plants. The
Village Creek plant, northwest of Birmingham, receives sewage
flow from most of the downtown Birmingham area.
The biological facility already had been upgraded and expanded
several times since it was first built in 1905 and currently
has a capacity of 60 million gallons per day. When torrential
downpours result in increased flows, wastewater can flow in
excess of 400 MGD. The excess has in the past been forced
to bypass the treatment plant, resulting in untreated sewage
going directly into Village Creek.
The new expansion is adding "peak flow facilities"
to provide full treatment for the high volume of wastewater
that flows to the plant during wet weather.
Birmingham-based Brasfield & Gorrie, ranked fourth among
the nation's top wastewater treatment contractors by Engineering
News Record, is a major contractor on the project. The firm
recently completed the Village Creek pumping station, a $44.94
million project, and 20 large surge basins in a $45.25 million
project.
Project manager Dennis Hill said that in times of peak flow,
the upgraded facility will pump stormwater into the new surge
basins. The stormwater will be aerated, partially treated
and held in these basins until the flow goes back down enough
so the water can be sent through the plant.
Hill said this job is big. "I've been working with the
company for 21 years now, and it seems like the plants get
bigger and bigger," he added. "It used to be a good-size
treatment plant could be built in 12 to 18 months. Now it
seems they're two to three years."
"There's a huge volume of work we have to do in a relatively
short period of time. Everything has to be coordinated closely.
You start at your deepest point and work your way up. You
have to make sure you don't install something too early. For
instance, a lot of electrical work has to be done, but it
can't be installed until near the end - you have to get the
piping in first."
The recently completed deep-pump station features eight pumps
that can pump 45 MGD each, and another four pumps that can
pump 15 MGD each. These are the largest sewage pumps in the
county, Hill said. The pump station required more than 26,000
cu. yds. of concrete. It's roughly 90 ft. below grade, with
a total height of about 120 ft. above the base floor slab.
On the pumping station, a big obstacle was a requirement in
the specs that backfill had to settle for six months before
laying pipe or pouring concrete on top of it. This spec made
it very difficult to complete the job in the 19 months allotted
in the contract.
Brasfield & Gorrie came up with an unusual solution. A
grid of concrete columns and grade beams, supported from the
bedrock, allowed workers to support the pipe and critical
structures such as transformer and generator pads without
waiting six months for the backfill to settle.
"As we brought our fill up from bedrock, we'd pour another
8 ft. of columns," Hill said. "We no longer had
to rely on the fill to support these things."
The biological facility is actually a number of structures.
There are eight large clarifiers, two pods of four each, requiring
more than 63,500 cu. yds. of concrete. The clarifiers are
140 ft. in diameter and 34 ft. high. "It's a pretty big
concrete structure," Hill said.
There are also large aeration basins, a blower building for
the aeration basins and the sludge thickeners. There's a pump
station for return-activated sludge and waste-activated sludge.
There is a tremendous amount of excavation and backfill involved
on the facility - close to 900,000 cu. yds. of material.
Then there's the pipe. For instance, a deep plant drain line
of 24-in. ductile iron pipe was more than 3,000 lin. ft long.
The project requires more than 39,000 lin. ft. of other iron
ductile yard piping, and more than 2,300 lin. ft. of steel
end ring RCP pipe, up to 120 in. in diameter.
One of the unusual features of the new facility is the offices
being built inside the water tank at the site.
"I used to build water tanks, and I've never seen someone
use one for an office facility," Hill said. Brasfield
& Gorrie put in floors and finished offices to create
three levels of offices inside the big steel column that supports
the water tank. By using this space for offices, the design
engineer reduced the total project cost.
Building it is much like building any other office space,
he said, "but there are no square corners," Hill
added. "We've built all shapes and sizes of office buildings
in our commercial building division, but this is pretty unique."
|