A Presidential
Address
Futuristic bridge serves as Clinton Library centerpiece
By George Waldon
The $97.1 million Clinton Presidential Library project in
downtown Little Rock hosted topping out ceremonies in May.
The placement of a final 29-ft. steel beam, bearing the names
of more than 5,000 donors, marked the progress of construction
at 35 percent complete. The 148,000-sq.-ft. structure is touted
as the largest building permit in the city's history.
It is envisioned as a futuristic truss bridge on the bank
of the Arkansas River. The design also serves as an allusion
to a catch phrase of the Bill Clinton while he was president:
Building a bridge to the 21st Century.
That vision translates into a pair of 420-ft. by 45-ft. trusses,
atop two 90-ft. cantilevers supported by drilled concrete
caissons. The 420-ft.-long building has three load bearing
points of caissons. The single foundation column on the north
end is crowned with a 95-ton girder, 50 ft. wide by 13 ft.
tall, and made of 6-in.-thick plate.
Workers had to drill 45 ft. to sink the caissons, and Rob
Hawkins, general superintendent for CDI Contractors Inc. of
Little Rock said that even though the soil reports indicated
soft shale, "it turned out to be much tougher drilling."
The harder rock formation was good for added stability, but
the surprise doubled the projected 45-day drilling schedule
for the piers. Despite the unexpected turn, adjustments to
the work schedule allowed the drilling to be completed within
a week of the planned delivery of the trusses.
The job was accomplished by modifying the original plan to
do the concrete work and steel erection concurrently. Concrete
was formed all the way up to keep the project moving, and
the steel was erected around it.
"We were able to switch from pouring the core shafts
to slip forming the stair towers and erecting the steel around
the concrete, which saved a lot of time," said Jonathan
Semans, program manager for Hensel Phelps Construction Co.
of Aurora, Colo.
The archives portion of the building is dominated by cast-in-place
concrete with waffle slabs. A radiant heating and cooling
system is integrated into the concrete.
The building will be encased with custom glass walls that
screen exhibits from ultraviolet light as well as reduce heat
gain from the sun. Building a point supported structural glass
wall off the trusses will be one of the more technical challenges
because it requires maintaining the truss alignments while
hanging more than 150,000 pounds of three-layer Pilkington
glass.
Plans called for a tolerance of + 1 3/8 in. on the alignment
of the top and bottom truss chords. The finished work ended
up coming in at + 3/4 in., prior to the glass work.
"The intricacy of the project is much higher than what
you normally see," said Danny Bennett, a project executive
with CDI Contractors.
Polshek Partnership Architects of New York City designed the
museum and archive facility.
Housed within the rectangle of a museum will be an exact replica
of the Oval Office, which is actually an ellipse.
The library is the centerpiece of the William J. Clinton Presidential
Center and Park, a $160 million development. The 27.7-acre
park, designed by Hargreaves Associates of Boston and San
Francisco, supplants a mix of old industrial and warehouse
properties.
The overall project is viewed as a catalyst for further significant
redevelopment in downtown Little Rock east of the I-30 bridge.
Construction officially started in June 2002, and steel erecting
began in November. The next milestone is to have the building
in the dry by December. Next summer should herald substantial
completion, with the exhibits' installation complete in fall
2004. Opening day remains slated for Nov. 18, 2004.
The lower three floors and basement will be devoted to the
museum and archives, with the fourth floor reserved as Clinton's
private executive living quarters.
The bridge motif also pays homage to the nearby Rock Island
Railway Bridge. Cut off from train traffic, the span will
be redeveloped into a walkway linking North Little Rock and
Little Rock as part of the overall presidential library development.
The nearby historic Choctaw Station, built in 1899 as a rail
passenger depot, will be converted to the Clinton School of
Public Policy and Foundation. Work is expected to begin this
summer on the 16,500 sq. ft. structure, which will house two
classrooms, library, common room and staff facilities.
Polk Stanley Yeary Architects Ltd. of Little Rock is overseeing
the design
on this facet of the project.
A large play area is also part of the development. It features
a design based on the concept of "An American Childhood"
and uses icons and exaggerated art forms of such elements
as blocks, tricycles, a tree house, marbles, leapfrog and
hopscotch to recreate the former president's playground memories.
|